The An Phu interchange in Ho Chi Minh City has had its completion date delayed until Q2/2026.

The 3.4 trillion VND interchange project in Ho Chi Minh City has had its completion schedule adjusted to Q2/2026 due to construction obstacles. The main components will be completed before the Lunar New Year 2026.

Báo Lâm ĐồngBáo Lâm Đồng17/12/2025

Project progress update

The Ho Chi Minh City People's Committee has officially approved adjusting the completion time of the An Phu traffic junction project to the second quarter of 2026, instead of the end of 2025 as originally planned. This decision was made based on a proposal from the Department of Construction to align with the actual implementation situation.

According to the new schedule, two key components must be put into operation before the Lunar New Year 2026. Specifically, the N2 bridge branch, allowing vehicles from the Ho Chi Minh City - Long Thanh - Dau Giay expressway to turn right onto Mai Chi Tho Boulevard (towards Vo Nguyen Giap road), must be open to traffic before December 31, 2025. The HC1-02 underpass, directly connecting Mai Chi Tho Boulevard with the expressway, must be completed before January 15, 2026.

The largest and most modern interchange project, costing over 3.4 trillion VND, in Vietnam's richest city, has missed its completion deadline - Photo 1.
The An Phu interchange is currently the largest and most modern interchange in Ho Chi Minh City. Photo: Tri Thuc Magazine

The remaining components of the project are expected to be completed in the second quarter of 2026.

Scale and strategic importance

The An Phu interchange project commenced in late 2022 with a total investment of over 3,400 billion VND. This is one of the key transportation projects, the largest and most modern in Ho Chi Minh City. The project is designed with three levels, including:

  • Basement: A two-way underpass connecting the Ho Chi Minh City - Long Thanh - Dau Giay Expressway with Mai Chi Tho Boulevard.
  • Ground level: Central circular island and branching islands.
  • Upper level: Two overpasses, including a Y-shaped bridge connecting Mai Chi Tho Boulevard and Luong Dinh Cua Street, and a bridge branching off from the expressway to cross Mai Chi Tho Boulevard.
The largest and most modern interchange project, costing over 3.4 trillion VND, in Vietnam's richest city, has missed its completion deadline - Photo 2.
Perspective view of the An Phu intersection after completion. (Illustrative image)

This interchange plays a crucial role as a major transportation hub at the eastern gateway of the city, connecting key arterial roads such as the Ho Chi Minh City - Long Thanh - Dau Giay Expressway, Mai Chi Tho Boulevard, Luong Dinh Cua Street, and Dong Van Cong Road leading to Cat Lai Port - the port with the largest cargo volume in the country.

The largest and most modern interchange project, costing over 3.4 trillion VND, in Vietnam's richest city, has missed its completion deadline - Photo 3.
Location of the An Phu intersection project. Graphic: VnExpress Newspaper

Reasons for the delay and current progress.

According to the investor, the Project Management Board for the construction of transportation infrastructure projects, the project has encountered many difficulties during construction due to the very high traffic density in the area, complex traffic organization, and obstacles related to the underground technical infrastructure system. To date, the construction volume of the entire project has only reached over 70% of the contract value.

Earlier, at the end of June, the HC1-01 underpass on Mai Chi Tho Boulevard was opened to traffic. However, because the underpass is not yet directly connected to the expressway, traffic congestion in the area has not improved significantly. Several other projects, such as the Ba Dat Bridge and the Giong Ong To Bridge, have been largely completed.

Accelerating the completion of the An Phu interchange will not only solve the traffic congestion problem at the eastern gateway but also create synergy and connectivity with future strategic infrastructure projects.

Source: https://baolamdong.vn/nut-giao-an-phu-tphcm-lui-tien-do-hoan-thanh-den-quy-ii2026-411255.html


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Enjoy the exciting night tours of Ho Chi Minh City.
A close-up view of the workshop making the LED star for Notre Dame Cathedral.
The 8-meter-tall Christmas star illuminating Notre Dame Cathedral in Ho Chi Minh City is particularly striking.
Huynh Nhu makes history at the SEA Games: A record that will be very difficult to break.

Same author

Heritage

Figure

Enterprise

A journey to explore Long Chau Lighthouse

News

Political System

Destination

Product