Vietnam.vn - Nền tảng quảng bá Việt Nam

Ho Chi Minh City: Construction accelerates on Tan Van interchange, the largest on Ring Road 3.

The Tan Van interchange is one of the six most complex and large-scale interchanges in the Ho Chi Minh City Ring Road 3 project, and construction is being accelerated with high intensity. The project is expected to alleviate traffic congestion at the northeastern gateway of the city and enhance inter-regional connectivity between Ho Chi Minh City and Dong Nai, aiming for completion in 2026.

Báo Tin TứcBáo Tin Tức12/12/2025

Photo caption
Photo caption
The Tan Van interchange is one of the six most important and complex interchanges of the Ring Road 3 project, playing a key role in connecting Ho Chi Minh City and Dong Nai province.

According to observations by reporters from the News and Nation Newspaper in mid-December, at the Tan Van interchange construction site, part of package XL1 of the Ring Road 3 project, hundreds of engineers and workers were working continuously on all three levels of traffic at the interchange.

This is the intersection of six major transportation arteries: Hanoi Highway, Metro Line 1, Ring Road 3, DT743A road, Nguyen Xien road, and Dong Nai Bridge, playing a crucial role in regulating traffic in the Southeast region.

Photo caption
Photo caption
Photo caption
Hundreds of workers, along with numerous machines and equipment, are accelerating progress at the Tan Van interchange.

The Tan Van interchange has a scale of 3 traffic levels and 5 overpass branches, requiring complex technical solutions under conditions of limited space and very high existing traffic volume. Currently, contractors are mobilizing maximum manpower and equipment to work around the clock.

Along National Highway 1, many concrete pillars for the overpass branch have been completed; construction teams are urgently working on the remaining pillars. The descending section of the elevated Ring Road 3 has entered the girder installation phase, while the third level, the most complex area of ​​the project, is being constructed at high intensity.

Photo caption
Photo caption
Photo caption
The bridge and road sections are currently under construction by workers and various machines.

Speaking to reporters, Mr. Nguyen Thanh Tan, Deputy Director of the XL1 project for the Tan Van interchange construction (formerly the Binh Duong Provincial Investment and Construction Project Management Board for Transportation Works), said: “The Tan Van interchange is approximately 2.5 km long, and to date, the progress of the XL1 project has reached about 45% of the contract volume. Currently, there are 7 contractors working on the bridge and road sections, and generally, they are all meeting the set schedule.”

Photo caption
Photo caption
Photo caption
Currently, there are over 200 workers on the construction site, working day and night.

According to Mr. Tan, the project is facing several difficulties, especially the scarcity of materials such as soil and stone, and price fluctuations leading to discrepancies compared to the contract price, putting pressure on the contractor to mobilize materials to the construction site. In addition, the prolonged heavy rain has affected the roadbed construction work.

Photo caption
Photo caption
Photo caption
Many concrete pillars for the overpass branch have been completed, and the construction teams are working urgently on the remaining pillars.

“When the weather is favorable, the Project Management Board will request contractors to increase equipment and personnel and work overtime to accelerate progress according to the plan. It is expected that the main elevated bridge will be completed for technical traffic by April 30, 2026; the parallel roads will be fully completed by June 30, 2026,” Mr. Nguyen Thanh Tan added.

Photo caption
Photo caption
Many sections of the route have been covered with crushed stone, awaiting asphalt paving and curb installation.

“Currently, there are more than 200 workers and engineers on the construction site, along with about 140 pieces of machinery and equipment. Bridge construction is progressing continuously, while road construction is working overtime to compensate for the rainy days. The Board will require the seven contractors to focus even more on machinery, manpower, and materials to ensure the overall progress of the project,” Mr. Tan emphasized.

The Ho Chi Minh City Ring Road 3, spanning 76.3 km and with a total investment of over 75,000 billion VND, passes through Ho Chi Minh City, Dong Nai, and Tay Ninh provinces. To date, approximately 63% of the construction work has been completed. If the progress is maintained, the project will be completed and put into operation in 2026, contributing to traffic congestion relief and opening up new development opportunities for the Southern key economic region.

Source: https://baotintuc.vn/anh/tp-ho-chi-minh-tang-toc-thi-cong-nut-giao-tan-van-lon-nhat-vanh-dai-3-20251211185221729.htm


Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Vietnam is the world's leading Heritage Destination in 2025

News

Political System

Destination

Product