Promoting the progress of the coastal road project through the Cua Tung and Cua Viet bridge areas

Việt NamViệt Nam04/05/2024

Today, May 4, Vice Chairman of the Provincial People's Committee Le Duc Tien chaired a meeting to speed up the progress of the coastal road project through the Cua Tung and Cua Viet bridges. Permanent Vice Chairman of the Provincial People's Council Nguyen Chien Thang attended the meeting.

The Coastal Road Project through Cua Tung and Cua Viet Bridges was approved by the Provincial People's Council in Resolution No. 129/NQ-HDND dated December 19, 2023; the Provincial People's Committee approved the feasibility study report in Decision No. 810/QD-UBND dated April 9, 2024.

Promoting the progress of the coastal road project through the Cua Tung and Cua Viet bridge areas

Standing Vice Chairman of the Provincial People's Council Nguyen Chien Thang speaks at the meeting - Photo: MH

The project is about 3.16 km long with a total investment of 600 billion VND from the central budget. The project implementation period is from 2024 to 2025. It is expected that the project will use 16.4 hectares of land; about 110 affected households will need to be relocated.

The problem in implementing the project is that in a short time, a large amount of land must be cleared, including a large area of ​​protective forest land, which takes a long time. Along with that, the capital source has not been allocated, so it is not possible to carry out appraisal and approval to implement the next steps.

Speaking at the meeting, Standing Vice Chairman of the Provincial People's Council Nguyen Chien Thang emphasized that the Provincial People's Council will work with the Provincial People's Committee to make every effort to arrange capital to promptly implement the project. Regarding site clearance, districts need to proactively develop resettlement plans, when calculating compensation support prices, if there are special cases, report to the Provincial People's Committee to promptly handle problems.

Concluding the meeting, Vice Chairman of the Provincial People's Committee Le Duc Tien requested that specialized agencies and consulting units absorb the opinions of Permanent Vice Chairman of the Provincial People's Council Nguyen Chien Thang and related sectors.

At the same time, he said that the central government's support of capital to implement the above project is a great opportunity for resources in the context of the province's difficult budget, so he suggested that the investor focus on developing a plan, fully preparing procedures, building a planning framework and processes to implement the project.

The Provincial People's Committee leaders are ready to support in promptly handling any problems and difficulties during the project implementation process. Regarding expertise, the Department of Transport will be assigned to appraise and ensure capital savings, safety and efficiency when the completed project is put into use.

Pham My Hanh


Source

Comment (0)

No data
No data

Same tag

Same category

Vietnam team promoted to FIFA rank after victory over Nepal, Indonesia in danger
71 years after liberation, Hanoi retains its heritage beauty in the modern flow
71st anniversary of Capital Liberation Day - stirring up the spirit for Hanoi to step firmly into the new era
Flooded areas in Lang Son seen from a helicopter

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product