Vietnam.vn - Nền tảng quảng bá Việt Nam

Close-up of the 800 billion dong road in the east of Ho Chi Minh City, about to reach the finish line after nearly 10 years of construction

Báo Giao thôngBáo Giao thông13/01/2025

Although only about 2.5km long, after nearly a decade of construction, Luong Dinh Cua Street is almost completed, opening a section of traffic before Lunar New Year 2025.


Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 1.

Located in the east of Ho Chi Minh City, Luong Dinh Cua Street connects many key traffic routes such as Mai Chi Tho, Tran Nao... and is considered a strategic route, contributing significantly to traffic circulation and promoting economic development in the region.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 2.

Since 2015, Luong Dinh Cua Street has been expanded to a scale of 30m, extending from Tran Nao Street to An Phu intersection with a total investment of more than 800 billion VND. However, the project has continuously been delayed, and construction has been sluggish and haphazard. In the photo is a 250m section of Luong Dinh Cua Street in early 2024 that has not yet been cleared, so construction cannot begin.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 3.

Up to now, the Traffic Construction Investment Project Management Board (Traffic Board - investor) has also set the completion time and traffic opening of a section of the project on January 20 (section from Nguyen Hoang Street to Tran Nao intersection).

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 4.

According to records, up to now, Luong Dinh Cua street section from Cao Duc Lan street to An Tu Cong Chua street has been basically completed, traffic is smooth. Meanwhile, the section from Nguyen Hoang street to Tran Nao intersection has not been completed, and is being urgently constructed by the contractor.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 5.

In the photo, Luong Dinh Cua street from Cao Duc Lan street to Nguyen Hoang street is being covered with crushed stone, the road surface is being compacted, and prepared for asphalt concrete paving.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 6.
Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 7.

Other items such as sidewalk curbing, stone paving, tree planting... are also being urgently implemented. At the construction site, there are dozens of workers working every day to ensure progress.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 8.
Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 9.

Many sidewalk sections are under construction and are expected to be completed in the next few days.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 10.

Ms. Nguyen Thi Hien, a resident on Luong Dinh Cua Street, said: "Life is affected, business is also affected, I just hope the road will be completed soon so that people can travel conveniently and business can also improve."

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 11.

The completion date for the Luong Dinh Cua section has been set, but the remaining section, from Nguyen Hoang Street to An Phu intersection (600m long), is still at a standstill. This is a section of road that is facing procedural difficulties, with 22,000m² of land belonging to the An Phu Development Urban Area project, invested by Thu Thiem Real Estate Joint Stock Company. This area involves 64 households that need to be cleared, but there is no consensus on responsibilities between the parties.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 12.

In addition, this 22,000m² area is in a state of "project overlapping project" with the construction of An Phu intersection. For many years, the road section has not been cleared of difficulties and obstacles for construction and expansion, so traffic congestion and jams have continuously occurred.

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 13.
Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 14.
Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 15.

The Department of Natural Resources and Environment of Ho Chi Minh City has proposed that the People's Committee of Ho Chi Minh City submit to the Prime Minister an adjustment to reduce the land area by 22,000m². The Traffic Department will be assigned to add about 10,054m² to the compensation plan of the An Phu intersection project; Thu Thiem Real Estate Joint Stock Company and related units must repay the compensation cost and continue to complete the technical infrastructure as required. (In the photo, the Luong Dinh Cua street section is shabby, overgrown with grass, causing loss of urban beauty).

Cận cảnh tuyến đường 800 tỷ phía đông TP.HCM sắp về đích sau gần 10 năm thi công- Ảnh 16.

With the remaining area, Thu Duc City People's Committee will review and renovate to develop residential areas, create favorable conditions for construction and improve the quality of life of local residents.



Source: https://www.baogiaothong.vn/can-canh-tuyen-duong-800-ty-phia-dong-tphcm-sap-ve-dich-sau-gan-10-nam-thi-cong-192250112153206065.htm

Comment (0)

No data
No data

Same tag

Same category

Keeping the spirit of Mid-Autumn Festival through the colors of the figurines
Discover the only village in Vietnam in the top 50 most beautiful villages in the world
Why are red flag lanterns with yellow stars popular this year?
Vietnam wins Intervision 2025 music competition

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product