The resettlement site was built with support from the Ministry of National Defense , the Military Region 2 Command was assigned as the investor, and the construction unit was the 789 Corporation - Ministry of National Defense.

On a land area of more than 3.5 hectares, the construction unit is building 60 houses designed in the traditional architecture of the Mong ethnic group.
According to the report of the construction unit, up to now, the rough construction of 42 houses has been completed, and the roofs of 20 houses have been roofed. Nearly 200 workers and engineers of the 789 Corporation and officers and soldiers of the 174th Regiment, 316th Division, Military Region 2 are regularly present at the construction site.
These days, the teams are continuing to complete the remaining houses, while also tiling the floors, painting the walls, and constructing the interiors of the roofed houses.

The biggest difficulty now is the rainy season, which affects the implementation of outdoor construction items. In addition, the construction site is covered with many large rocks, which also slows down the progress of leveling the ground and building the house foundation.