On the afternoon of September 23, Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Lam Dong province Ho Van Muoi chaired a conference to assess the socio -economic situation, national defense and security in the first 9 months and deploy key tasks for the last months of 2025. The conference was held online to communes, wards and special zones in the province.
Speaking at the opening of the conference, comrade Ho Van Muoi said that after nearly 9 months, many important economic indicators of the province have not yet met the requirements, such as the economic growth rate reaching 6.8%, the proposed scenario is 7.46%; disbursement of public investment capital only reached 23.4% of the plan, if the completed volume that has not been paid is included, the disbursement rate reaches about 27% of the plan.
With this result, Lam Dong is lower than the national average disbursement level and ranks 30th. Therefore, the most important goal of the province in the last months of the year is to disburse public investment capital .
According to the Department of Finance of Lam Dong province, as of August 31, the total disbursed capital for the 2025 and 2024 plans extending to 2025 had only reached 4,492/18,904 billion VND. If the completed volume of more than 699 billion VND that has not been paid is added, the disbursement rate would reach about 27% of the plan.
The allocation of key projects alone is 7,962.8 billion VND, accounting for 42% of the total planned capital for 2025 in the province. To date, more than 430 billion VND has been disbursed, reaching 5% of the plan.
According to analysis, disbursement of public investment capital in Lam Dong faces many difficulties due to projects being included in the zoning plan for exploration, exploitation and ore processing; problems in licensing land exploitation for filling materials in areas with mineral planning; and slow completion of Project Management Boards.
At the same time, the leadership and direction of some sectors, localities and investors have not been truly determined, not closely and specifically in order to completely handle arising difficulties and problems; site clearance work has been implemented very slowly; construction contractors and consulting units are still weak... greatly affecting the progress of project implementation and disbursement of public investment capital.
Chairman of Lam Dong Provincial People's Committee Ho Van Muoi emphasized that disbursement of public investment capital is one of the very important tasks. If by the end of 2025, the disbursement of capital is not achieved, Lam Dong will fail to achieve its socio-economic targets. Currently, all basic mechanisms and procedures have been completed, if the disbursement of public investment capital is not achieved, do not use the excuse of mechanisms and policies.
He requested that departments, branches and localities regularly pay attention to and remember this task every day and coordinate, accompany, unify, and resolve difficulties to successfully complete the plan for disbursing public investment capital in the locality.
* In the first 9 months of 2025, Lam Dong's economic growth rate reached 6.8%; budget revenue reached 23,592 billion VND, reaching 84% of the local estimate, up 19.1% over the same period in 2024; 37 new non-budget investment projects were granted, with a total registered investment capital of more than 13,706 billion VND, land use area of about 673.7 hectares; total export turnover reached more than 2,457 million USD, reaching 79.8% of the plan, up 20.5% over the same period in 2024.
* The total number of visitors to Lam Dong for sightseeing and relaxation is more than 15.2 million, an increase of nearly 17.6% over the same period in 2024. Of which, international visitors reached 915 thousand, an increase of more than 33.1%; revenue from tourism activities is more than 40.2 trillion VND, an increase of 18.36% over the same period in 2024.
Source: https://baolamdong.vn/lam-dong-tap-trung-giai-ngan-von-dau-tu-cong-392830.html