BPO - On the morning of May 13, Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee Le Truong Son worked with the People's Committees of Hon Quan district and Binh Long town on the approval of land prices and compensation plans for the expanded corridor in Hon Quan district and Binh Long town, belonging to the 110kV transmission line phase division project from Binh Long to My Phuoc.

Báo Bình PhướcBáo Bình Phước13/05/2025

The 110kV transmission line phase-out project from 177 Binh Long 2 to 175 My Phuoc passes through 3 communes of Phuoc An, Tan Loi and Thanh Binh of Hon Quan district, with a total length of 4,009km. The project affects 61 households and individuals, with 168 plots of land affected.

Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee Le Truong Son spoke at the meeting.

To date, the People's Committee of Hon Quan district has completed the inventory of assets and crops, approved specific land prices to calculate compensation for households in the project. At the same time, the detailed compensation and support plan has been completed and is being consulted with the people.

Leaders of departments, agencies, units and localities attended the working session.

Leaders of Binh Long Town People's Committee reported at the meeting

Mr. Nguyen Vu Tien, Vice Chairman of Hon Quan District People's Committee reported at the meeting.

Representative of Southern Power Corporation speaking at the meeting

Leaders of the Department of Industry and Trade spoke at the meeting

At the meeting, representatives of the People's Committee of Hon Quan district, Binh Long town and communes where the project passes through raised some difficulties in the implementation process. Specifically: Some households do not agree with the application of land prices and compensation for crops based on reality; people request that rice land must still be compensated for crops and supported to limit land use.

Speaking at the meeting, Vice Chairman of the Provincial People's Committee Le Truong Son requested departments, agencies and localities to coordinate closely and regularly grasp the actual situation. Localities must maintain the working spirit, not let the adjustment of the district-level organizational structure affect the progress of problem solving; must not be subjective in grasping the situation, ensuring the progress of implementation and settlement of administrative procedures; compensation and site clearance work must be carried out synchronously with mobilization and propaganda to create consensus among the people.

The Vice Chairman of the Provincial People's Committee requested relevant parties to remove difficulties and obstacles and complete site clearance work before June 15, 2025.

Source: https://baobinhphuoc.com.vn/news/4/172698/thao-go-vuong-mac-va-hoan-thanh-giai-phong-mat-bang-truoc-ngay-15-6