Lam Dong Department of Construction said that on November 24, the Ministry of Construction issued a Decision to declare an emergency situation regarding natural disasters on Mimosa Pass.

Báo Lâm ĐồngBáo Lâm Đồng25/11/2025

The decision aims to promptly handle serious damage to traffic infrastructure caused by storm No. 13 and post-storm circulation from November 18 to 20, 2025.

tham-da-mimosa(1).jpg
Vice Chairman of the Provincial People's Committee Nguyen Hong Hai inspected the temporary road construction work at the Mimosa Pass construction site at noon on November 25.

The area identified to have suffered damage is located at Km226+600 - Km226+800 (design route Km3+600 - Km3+800), part of the project to renovate and upgrade the section through Mimosa Pass and some items on National Highway 20, managed by Project Management Board 85.

mimosa-sua.jpg
The temporary road is being paved and rolled. Work is expected to continue day and night to ensure completion by the 28th, then open to traffic on the 29th.

Immediately after announcing the emergency situation, the Ministry of Construction directed relevant units to deploy remedial work according to regulations.

Specifically, the Ministry of Construction directed the Department of Economics - Construction Investment Management to review, determine the extent of damage, propose repair solutions and issue an Emergency Construction Order to remedy the consequences.

Project Management Board 85 is the unit responsible to the Minister of Construction for the contents of reports on damage and deterioration of infrastructure.

The Department of Transport and Traffic Safety is also assigned to urge and guide units to deploy remedial work.

Serious landslides completely paralyzed Mimosa Pass.
Serious landslides have caused Mimosa Pass to collapse. A bridge will be built on this section to ensure long-term traffic safety.

Currently, in phase 1, at this section, Project Management Board 85 is urgently leveling and opening a temporary road, ensuring the completion of technical asphalt by November 28, and is expected to officially open to traffic on November 29, 2025.

The Ministry of Construction has agreed on a long-term plan to build an overpass at the damaged location to ensure sustainable traffic safety. Phase 2 of the project will start in mid-December and is expected to take about three months to complete.

Source: https://baolamdong.vn/bo-xay-dung-cong-bo-tinh-huong-khan-cap-len-phuong-an-xay-cau-tai-deo-mimosa-405115.html


Comment (0)

No data
No data

Same tag

Same category

Traveling to "Miniature Sapa": Immerse yourself in the majestic and poetic beauty of Binh Lieu mountains and forests
Hanoi coffee shop turns into Europe, sprays artificial snow, attracts customers
The 'two-zero' life of people in the flooded area of ​​Khanh Hoa on the 5th day of flood prevention
4th time seeing Ba Den mountain clearly and rarely from Ho Chi Minh City

Same author

Heritage

Figure

Enterprise

Hanoi coffee shop turns into Europe, sprays artificial snow, attracts customers

News

Political System

Destination

Product