Vietnam.vn - Nền tảng quảng bá Việt Nam

Độc lập - Tự do - Hạnh phúc

Deadline for completion of 2 key connecting routes in the South

TPO - The Ho Chi Minh Highway through Ho Chi Minh City will be completed and put into use this year. Meanwhile, the Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway will open to traffic in the third quarter of 2027.

Báo Tiền PhongBáo Tiền Phong01/09/2025

According to the reporter, the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project is under construction at the intersection with the Bac Tan Uyen - Phu Giao - Bau Bang dynamic road. The construction site is rubber forest land under the management of Phuoc Hoa Rubber Company. After receiving the handover of nearly 10 km, the contractor has mobilized hundreds of machines and human resources for construction. This is the first formed section of the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway, with a total length of more than 52 km.

2.png
The Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway is under construction for a nearly 10 km section in the middle of a rubber forest.

The total investment capital for this expressway project is over 17,000 billion VND, of which 8,833 billion VND is for construction costs, the rest is for site clearance compensation and other costs. The total land area to be recovered for project construction is about 344 hectares with 1,616 households affected.

This expressway project started in February, but due to difficulties in site clearance, the construction progress was affected. In 2024, only over VND 8.6 billion was disbursed; this year, over VND 1,663 billion was disbursed.

The reason for the slow site clearance work given by localities and units is that the implementation of a two-level local government system means that tasks that previously belonged to the district level are now transferred to the commune level, causing some delays.

Currently, the authorities of Ho Chi Minh City are coordinating to speed up the progress of compensation, site clearance, and handover to the construction contractor. According to the plan, the Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway will be completed in September 2027.

cao-toc.jpg
Location of Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway at the intersection with the Bac Tan Uyen - Phu Giao - Bau Bang dynamic road.

To keep up with the project's schedule, the HCMC People's Committee has required staff from relevant departments and units to have a daily and monthly plan of what to do, and work overtime to make up for the time spent focusing on operating the two-level government.

The Ho Chi Minh City Department of Construction has just reported to the Vietnam Road Administration on the implementation status of the Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway project (section through Ho Chi Minh City). According to the Ho Chi Minh City Department of Construction, the source of earth filling materials in the city is currently scarce due to the simultaneous implementation of many other projects.

The Ho Chi Minh Road project, Chon Thanh - Duc Hoa section passing through Dong Nai, Ho Chi Minh City and Tay Ninh, is 72.75 km long, divided into 3 construction packages with a total investment of about 2,293 billion VND.

Ho Chi Minh Road is built according to technical standards equivalent to a level III plain road, in the final stage of a 6-lane highway. Currently, the asphalt concrete paving has almost been completed along this route.

The 31.5 km Ho Chi Minh Road section through Ho Chi Minh City was scheduled to open to traffic on April 30, 2025, but land acquisition issues led to a delay. The project is part of the main route, mainly focusing on the Chon Thanh - Duc Hoa section, which has been restarted since late 2023 and is being accelerated to complete by the end of 2025.

5.jpg
6.jpg
Ho Chi Minh Road section in Ho Chi Minh City

This route passes through Dong Nai, Ho Chi Minh City, Tay Ninh, connecting with other important traffic axes, contributing to creating economic development momentum for the key economic region in the South.

The contractor representative said that the delay in handing over the site has greatly affected the construction progress and the project completion plan. If the locality does not handle the situation thoroughly, it will be very difficult for the contractor to complete the task as committed.

Car traffic temporarily suspended on Binh Trieu 1 bridge, traffic jam at the gateway to Ho Chi Minh City

Car traffic temporarily suspended on Binh Trieu 1 bridge, traffic jam at the gateway to Ho Chi Minh City

Before the opening day, electric wires still 'trap' the road to Nhon Trach bridge

Before the opening day, electric wires still 'trap' the road to Nhon Trach bridge

Image of the largest bridge on Ho Chi Minh City's Ring Road 3 before its opening day

Image of the largest bridge on Ho Chi Minh City's Ring Road 3 before its opening day

Source: https://tienphong.vn/chot-han-ve-dich-2-tuyen-duong-ket-noi-trong-diem-phia-nam-post1773931.tpo


Comment (0)

No data
No data

Same tag

Same category

Precariously swinging on the cliff, clinging to the rocks to scrape seaweed jam at Gia Lai beach
48 hours of cloud hunting, rice field watching, chicken eating in Y Ty
The secret of the Su-30MK2's top performance in the sky of Ba Dinh on September 2
Tuyen Quang lights up with giant Mid-Autumn lanterns during the festival night

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product