Partial opening of park to welcome visitors during the holidays
Amidst the harsh sunny and windy days of Vung Tau beach, at the construction site of Bai Sau coastal park, the working atmosphere is taking place urgently, groups of workers are diligently completing the final items. The project is expected to be partially opened in time for the April 30 holiday, bringing a new entertainment space to residents and tourists.
![]() |
On April 30 this year, Vung Tau will test opening a part of the marine park from Phan Chu Trinh to The Imperial Hotel. |
While working hard to pave the walkway, construction worker Nguyen Van Toan shared: “I have been involved in this project for more than four months. At first, I was not used to the sea weather, hot sun, wind and sand, so I was quite tired. But now I am used to it, especially in recent weeks when I have to work overtime continuously to keep up with the progress. Working on the beach is very sunny and windy, but hearing people passing by praise the beautiful project makes us happy and more motivated.”
According to the plan, on the occasion of April 30 this year, Vung Tau City will put into trial operation a part of the completed sea park, from Phan Chu Trinh Street to The Imperial Hotel. This is an area with many highlights such as granite walkways, cool green lawns, a sea-view bridge, a check-in gate and a typical culinary area. This new space is expected to become an attractive sightseeing and relaxation spot during the peak holiday season.
To ensure the safety of visitors, unfinished areas will be cordoned off, fenced off, with specific instructions and on-site support staff.
![]() |
This space promises to be an attractive destination during peak holidays. |
Mr. Doan Hai Linh - Acting Director of the Vung Tau City Land Fund Investment and Development Project Management Board said: "Although there are still many unfinished items in the project, we are determined to complete a part so that people can experience it on the occasion of April 30. The management board has mobilized all human resources, encouraged engineers and workers to work day and night to meet the schedule."
Project of over 1,000 billion VND, changing the face of coastal urban areas
The Thuy Van - Bai Sau road improvement project started in October 2024 with a total investment of more than 1,000 billion VND. This is one of the city's key projects, aiming to improve tourism infrastructure and coastal public spaces.
The total area of the project is about 17.06 hectares, covering the entire public park area and 3.2 km long beach along Thuy Van Street, the main tourist route of Vung Tau City. The project is divided into many functional spaces including: Green park area, central square area, open space and highlight works, reasonably arranged for community and tourism activities, synchronous utility system, including lighting, landscape, public sanitation and internal traffic.
![]() |
The project is 17.06 hectares wide, stretching 3.2 km along the main tourist route Thuy Van of Vung Tau City. |
Putting Bai Sau Beach Park into operation not only helps improve the quality of life for people but also contributes to enhancing the tourism image of Vung Tau as a dynamic, modern and friendly coastal city.
It is expected that the number of tourists flocking to Vung Tau during the April 30 holiday will increase. This modern marine park promises to become a new destination, enhancing the experience for residents and tourists, while creating momentum to promote sustainable development of coastal services and trade activities.