Vietnam.vn - Nền tảng quảng bá Việt Nam

List of projects with fast public investment disbursement in Hai Duong

Thanks to synchronous implementation, many projects in Hai Duong have rapid investment capital disbursement progress.

Báo Hải DươngBáo Hải Dương09/06/2025

short-term-project(1).jpg
Currently, contractors for the investment project to build the extended provincial road 396 (the section connecting provincial road 391 to provincial road 390) are deploying more than 10 construction fronts.

Fast construction, timely disbursement

The investment project to build the extended Provincial Road 396 (the section connecting Provincial Road 391 to Provincial Road 390), located in Thanh Ha and Tu Ky districts, started construction in July 2024. In recent days, taking advantage of favorable weather, contractors have mobilized maximum human resources and vehicles to speed up construction progress.

Currently, construction units are deploying more than 10 construction teams in the bidding packages. Particularly in Tu Ky district, the contractor is deploying 2 bored pile construction teams in the Thai Binh River overpass area, 1 beam casting team, 1 sand filling team and roadbed.

This project aims to complete the regional transport infrastructure network, form the province's belt axis, connect and promote socio -economic development in neighboring areas. The total investment of the project is 846.42 billion VND, the main route length is about 7.61 km (including 3.66 km through Thanh Ha district and 3.95 km through Tu Ky district). The road is expected to be completed in December 2025.

Mr. Tran Ngoc Duong, representative of the joint venture contractor Viet Hoa Construction and Trading Joint Stock Company, said: “To ensure progress, we always maintain 5-6 construction teams along the entire route, working in 3 shifts, 4 teams regardless of day or night. Each completed volume is closely coordinated with the investor for timely acceptance, payment and capital disbursement.”

By the end of May, the project had disbursed more than 76 billion VND, reaching more than 50% of the capital plan assigned in 2025, exceeding 38% of the scenario plan.

The project to build an interchange connecting National Highway 17B with National Highway 5 and the Hanoi - Hai Phong railway is also being accelerated. The project has a total investment of VND 1,867 billion, started at the end of December 2024 and is expected to be completed in December 2025. In 2025, the capital plan assigned to the project is nearly VND 535 billion. By the end of May, the project had disbursed more than VND 303 billion, reaching about 60% of the annual plan, exceeding 50% compared to the scenario plan of the Provincial People's Committee.

Mr. Vu Quoc Huong, the project's chief supervisor, said: "The construction value of the project is about 800 billion VND. This is a key project, so progress and quality are always top priorities. Although the price of raw materials has increased, thanks to timely disbursement, the progress is still guaranteed."

Stick to the script, exceed schedule

communication-project(1).jpg
By the end of May 2025, the project to build an interchange connecting National Highway 17B with National Highway 5 and the Hanoi - Hai Phong railway had disbursed more than 303 billion VND, reaching about 60% of the annual plan, exceeding 50% compared to the scenario plan of the Provincial People's Committee.

The project to build Van road and bridge, connecting National Highway 37 (Chi Linh city) with Trieu bridge approach road (Kinh Mon town), has a total length of about 13.07 km (main route 9.7 km, two branch routes 3.37 km long), with a total investment of 1,296 billion VND.

The project passes through many communes and wards with large and complicated land clearance areas. However, with the determination of the authorities of Chi Linh City and Kinh Mon Town, the land clearance work has been implemented synchronously, handing over to where, construction is carried out. Up to now, the two localities have basically completed the land clearance, creating conditions for contractors to carry out construction.

Since the beginning of the year, the project has disbursed nearly VND246 billion, reaching 89.5% of the 2025 capital plan and exceeding the scenario plan by 347%. This is also the project with the highest disbursement rate in the first 5 months of the year in the province.

According to the Hai Duong Provincial Department of Finance, the province's total public investment capital plan for 2025 is nearly VND11,400 billion, an increase of about VND1,000 billion compared to the plan assigned by the Prime Minister. By the end of May, the whole province had disbursed more than VND4,200 billion, reaching 37.4% of the plan assigned by the province and 40.7% of the plan assigned by the Prime Minister, higher than the national average (22%) and faster than in recent years.

This positive result was achieved thanks to the province's implementation of many synchronous solutions to ensure the feasibility of public investment capital disbursement. In particular, the disbursement plan was developed in detail for each month, each quarter, and each project. Departments and branches were directed to actively shorten the appraisal time. Leaders at all levels regularly inspected and urged the compensation and site clearance work in each locality and project. Units and localities also regularly reviewed and evaluated the progress and disbursement capacity, thereby promptly adjusting the capital plan in accordance with reality.

quick-short-answer-1(1).jpg
The bidding packages for the investment project to build the extended provincial road 396 (the section connecting provincial road 391 to provincial road 390) will be completed as soon as the construction is completed, the contractor and the investor will immediately finalize the disbursement volume.

In 2025, the Provincial Construction Investment Project Management Board was assigned more than VND5,000 billion to implement 65 projects. In the first 5 months of the year, the unit disbursed nearly VND1,800 billion, reaching 35.3% of the capital plan. Of the 65 projects, 44 projects are under construction, 15 projects exceeded the disbursement plan, and 4 projects are on schedule.

The progress of disbursement of public investment capital currently depends mainly on site clearance. Construction can only begin when the site is handed over. In addition, the high price of construction materials and the scarcity of supply also greatly affect the progress.

With the high determination of Party committees and authorities at all levels, the close coordination of departments and branches, and the efforts of investors and contractors to overcome difficulties, Hai Duong expects to complete early and exceed the public investment disbursement plan for 2025.

To promote the disbursement of public investment capital, the Hai Duong Provincial Construction Investment Project Management Board regularly inspects construction sites and closely coordinates with specialized agencies to shorten appraisal time, helping projects start construction soon. On the 15th-20th of each month, the board coordinates with contractors to review the volume and prepare timely payment and settlement records.

HA VY

Source: https://baohaiduong.vn/diem-danh-nhung-du-an-giai-ngan-von-dau-tu-cong-nhanh-tai-hai-duong-413581.html


Comment (0)

No data
No data

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product