On June 14, the Supervisory Delegation of the Economic - Budget Committee of the Provincial People's Council conducted a thematic supervision of the results of the implementation of the Industrial - Handicraft Development Program (IN - TTCN) of Hung Yen province for the period 2021 - 2025, with a vision to 2030 in a number of industrial clusters (ICs) in the province.
At the industrial parks, representatives of the units reported to the monitoring delegation on the implementation of the industrial parks: Phung Chi Kien, Dong Than, Pham Ngu Lao - Nghia Dan, Quang Lang - Dang Le. Up to now, Phung Chi Kien industrial park has cleared 41 hectares of land, reaching over 86% of the total infrastructure area; 1 project has been granted an investment registration certificate by the Department of Planning and Investment in Phung Chi Kien industrial park with an area of about 30.5 hectares.
For Dong Than Industrial Park, the investor of the industrial park infrastructure has coordinated with departments, branches and Yen My district to clear nearly 27 hectares, reaching 35% of the total area that needs to be recovered to implement the project.
Pham Ngu Lao - Nghia Dan Industrial Park has cleared over 74 hectares, reaching 99.2% of the total area to be recovered; the investor is in the process of investing in building technical infrastructure to receive investment projects in the industrial park. Currently, 8 enterprises have been granted Investment Registration Certificates by the Department of Planning and Investment in Pham Ngu Lao - Nghia Dan Industrial Park with a total area of 8.8 hectares.
Quang Lang - Dang Le Industrial Park has completed site clearance work and is in the process of building technical infrastructure to prepare to receive investment projects.
Representatives of infrastructure investors of industrial parks requested the province to pay attention to removing difficulties in site clearance work, speeding up project implementation progress; removing difficulties and obstacles related to investment procedures...
At the industrial parks, the monitoring team requested the infrastructure investors of the industrial parks to clarify the contents in the implementation of the projects. In which, the contents focused on: Difficulties and obstacles in the process of project implementation; attracting and managing the activities of investment projects in the industrial parks... At the same time, the units were requested to complete the report and send it to the Economic - Budget Committee for synthesis and reporting to the Provincial People's Council.