According to the investor's report, up to now, the total cleared area of the project is 210.58 hectares, reaching 93.24% of the total area of land that needs to be recovered. For residential land, localities have completed the work of counting and determining the origin of the land; basically completed the compensation and support plan for residential land; currently, the compensation and support plan for residential land and the resettlement plan are being publicized and completed; some localities have approved the plan and issued decisions to recover residential land. The construction unit has completed about 52.66% of the contract value...
Inspecting the actual situation at the site, Vice Chairman of the Provincial People's Committee Nguyen Hung Nam requested localities to mobilize resources and focus on implementing well the work of land clearance for residential land areas. In particular, urgently publicize the compensation plan and resettlement arrangement for households. Focus on propaganda and mobilizing people to understand the purpose, meaning and benefits of the project, creating high consensus in handing over the site, creating favorable conditions for the construction unit. Departments and branches guide localities on compensation procedures, support for land clearance, resettlement arrangement... The construction unit mobilizes maximum machinery, equipment, human resources, commands the construction teams to coordinate smoothly, speeding up the construction progress of the sections with cleared land. The investor strengthens the inspection and supervision work, ensuring the progress and quality of the project...
Source: https://baohungyen.vn/dong-chi-pho-chu-cich-ubnd-tinh-nguyen-hung-nam-kiem-tra-tien-do-trien-khai-du-an-dau-tu-xay-dung-du-3182587.html
Comment (0)