According to the conclusion of the Dong Nai Provincial Inspectorate, regarding the compliance with the law in the work of establishing, appraising, approving and adjusting construction planning, it was discovered that 4 planning projects were behind schedule in terms of schedule. 1 planning project was behind schedule in terms of schedule. 8 projects were behind schedule in terms of schedule. This responsibility belongs to the Department of Construction of Dong Nai Province.
The establishment, appraisal and approval of the 1/5,000 scale planning of subdivision A9 for Bui Huu Nghia Street (Bien Hoa City) with the road width reduced from 33 m to 26 m. The green park and public works area reduced from 66 ha to 19.1 ha, which is not consistent with the general planning of Bien Hoa City approved in 2014, is a violation of the provisions of Clause 4, Article 26 of the 2009 Law on Urban Planning.
Regarding the overall adjustment project of the detailed construction planning project at a scale of 1/500 for the resettlement area in Long Phuoc commune (Long Thanh district), the inspection showed that the Long Thanh District Project Management Board had not prepared a complete planning task dossier according to regulations... The responsibility belongs to the Long Thanh District Project Management Board.
Notably, the 3 projects that were established, appraised and approved without the arrangement of educational facilities are not in accordance with regulations. These are the detailed planning project 1/500 of the Residential and Commercial Service Area project in Tay Hoa commune (Trang Bom district) invested by Lien Hop Real Estate Company Limited. The 7-hectare planned residential area in Trang Bom town (Trang Bom district) invested by Le Huong Son Company Limited. The planned residential area in Trang Bom town invested by Le Bao Minh Company Limited...
In the detailed planning project 1/500 of the residential and commercial service project in Tay Hoa commune, the investor built a number of rows of houses with a length of over 60 m but did not arrange traffic roads with a minimum width of 4 m between the rows of houses, which is not in accordance with regulations.
Through inspection of the organization of construction planning implementation in some planning projects, it was discovered that there are still shortcomings and limitations. The planning project for workers' and residents' housing in Bac Son commune (Trang Bom district) has been implemented too slowly since 2000 until now (23 years), the project had to adjust the planning many times, causing waste of resources. The responsibility belongs to Bao Giang Company Limited.
The establishment of Quang Trung Industrial Cluster (Quang Trung Commune, Thong Nhat District) with an area of 79.87 hectares is not in accordance with regulations. This leads to the establishment, appraisal and approval of the detailed construction planning project at a scale of 1/500 of Quang Trung Industrial Cluster project with an area of 79.87 hectares being inappropriate.
In the detailed construction planning project at a scale of 1/500 of the Quang Trung commune cemetery project (Thong Nhat district), through inspection, it was determined that the investor carried out the construction of a part of N3 road not in accordance with the granted construction permit" which is a violation of Clause 4, Article 12 of the 2014 Construction Law which stipulates prohibited acts of "constructing works not in accordance with the granted construction permit". The investor's signing of 6 contracts with service users is not in accordance with the prescribed procedures. The responsibility belongs to Nirvana Memorial Park Company Limited.
Regarding the implementation of the overall adjustment project of the detailed construction planning at a scale of 1/500 of the residential area project in Thong Nhat ward (Bien Hoa city), it shows that Berjaya D2D Company built a swimming pool to serve the residents of the Amber Court apartment building not in accordance with the approved planning (green park land), which is a violation of Clause 4, Article 12 of the Construction Law 2014.
Notably, the Dong Nai Industrial Parks Management Board has not promptly inspected to detect the illegal construction of Y Cuong Thinh Trading and Service Company Limited.