Technical traffic opening of Ho Chi Minh City Ring Road 3 section through Tay Ninh before December 19

On the morning of July 12, Minister of Construction Tran Hong Minh and his delegation conducted a field survey and listened to a progress report on the Ring Road 3 project at the intersection with Ho Chi Minh City - Trung Luong Expressway and Ben Luc - Long Thanh Expressway, through My Yen Commune, Tay Ninh Province.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng12/07/2025

After surveying the site and listening to the progress report, Minister of Construction Tran Hong Minh requested the completion and technical opening of the Ring Road 3 section through Tay Ninh before December 19.

bo-truong-tran-hong-minh-kiem-tra-vanh-dai-3-16-17522868519231574178689.jpg
Minister of Construction Tran Hong Minh conducts a field survey

Currently, the site clearance work for this section has been 100% completed, the resettlement area has been completed and all plots of land have been handed over to affected households, the 3 main packages of the project are being constructed simultaneously, reaching about 78% of the construction volume. Regarding the disbursement progress, so far it has only reached more than 20% compared to the capital plan for 2025.

vanh-dai-3-qua-long-an-3-1752292135710855981230.jpeg
Intersection of Ring Road 3 project with Ho Chi Minh City - Trung Luong expressway and Ben Luc - Long Thanh expressway, section through Tay Ninh province

It is expected that the main roadbed will be completed with crushed stone before August 31, the asphalt pavement will be paved by the end of September and the technical traffic will be opened by the end of October 2025. The bridge section will complete the beam launching and concrete pouring in August, then asphalt and railing installation in September. The intersections with the two expressways Ho Chi Minh City - Trung Luong and Ben Luc - Long Thanh will also be constructed synchronously, with the same progress schedule of foundation completion at the end of August, asphalt pavement at the end of September and technical traffic opening before October 31.

The Ho Chi Minh City Ring Road 3 project, the 6.8km section through Tay Ninh, includes two component projects with a total investment of VND4,208 billion, of which construction costs are VND3,040 billion and site clearance and resettlement costs are more than VND1,160 billion.

Source: https://www.sggp.org.vn/thong-xe-ky-thuat-duong-vanh-dai-3-tphcm-doan-qua-tay-ninh-truoc-19-12-post803510.html


Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product