According to Decision 2972, unit price is the basis for developing a bid package estimate in case of applying the bidding method or developing a price plan in case of applying the ordering method for solid waste collection and disposal services on rivers and canals with waterway traffic functions in Ho Chi Minh City.
Accordingly, the unit price includes labor costs and construction machine costs. In which, labor costs in the unit price are determined by multiplying the labor cost norm to perform a unit of work volume by the corresponding labor unit price (VND/work) in each work.
Construction machine costs in the unit price are determined by multiplying the construction machine loss rate to perform a unit of work volume (loss rate) by the construction machine unit price (VND/shift) corresponding to each type of machine in each work.

For the work of collecting trash on the surface of canals and ditches by boat, the tasks include: checking the vehicle, working tools and labor protection equipment; Moving the vehicle to the trash collection location; Workers use a net to collect trash and put it in a net bag, the operation is repeated continuously...
For the work of collecting water hyacinth, seaweed, and waste on canals and ditches by 90CV barges, it is carried out on canals and ditches with a water surface area convenient for barge movement and with regular flow.