Restarting the construction project of Phan Boi Chau High School for the Gifted

After many years of implementation, the Phan Boi Chau High School for the Gifted project has not yet been completed on schedule. Therefore, to put it into use soon, it is necessary to speed up the construction and promptly supplement capital sources according to the proposed plan.

Báo Nghệ AnBáo Nghệ An27/11/2025

Speed ​​up construction progress

After a period of temporary suspension of construction, from mid-2025, the project to build a new Phan Boi Chau High School for the Gifted has been restarted. On the morning of November 27, at the construction site, all items of phase 2 of the project are under construction. These are the dormitory area for students, the office building for teachers and some other items such as the cafeteria, water tank, surrounding fence...

Photo - My Ha (7)
After nearly 3 years of interruption, phase 2 of the new construction project of Phan Boi Chau High School for the Gifted was restarted in early June 2025. Photo: My Ha

Sharing about the implementation process, Mr. Tran Long - Deputy Project Commander said: Phase 2 of the Phan Boi Chau High School construction project started construction in June 2025 and up to now, all items are in the process of rough construction, implementing on schedule. According to the plan, by early 2027, the construction of items of phase 2 will be completed, but we are trying to speed up the progress to be able to hand over in mid-2026.

Previously, the project to build a new Phan Boi Chau High School for the Gifted was approved by the Provincial People's Committee in 2018 with the goal of building Phan Boi Chau High School for the Gifted into a high-quality key school. The new school was built on a total area of ​​85,233 m², located in the two communes of Nghi Phong and Nghi An (old Vinh city), now Vinh Loc ward.

Photo - My Ha (3)
The classroom block of phase 1 of the project has been completed. Photo: Tien Hung

Immediately after approval, phase 1 of the project with an investment cost of 95 billion VND invested by the Department of Education and Training, with items such as classrooms, functional rooms, libraries and connected to each other through the bridge corridor system was completed in 2022.

Immediately after phase 1 , day On February 28, 2023, the People's Council of Nghe An province approved Resolution No. 05/NQ-HDND on the investment policy of the project: Construction of a new Phan Boi Chau High School for the Gifted (Phase 2), with a total investment of nearly 101 billion VND, with many items such as: Headquarters building, dining hall, student dormitory and some other items. However, since the project was approved, due to lack of capital and many other reasons, the project has not been constructed. For a long time, due to a nearly 3-year interruption, some items have been damaged and degraded.

Accelerate funding early

Phan Boi Chau High School for the Gifted is the most successful school in Nghe An and is in the top of the quality list of specialized schools in the country. With the important role in developing high-quality education in the province in particular and the North Central region in general, on June 12, 2020, the Prime Minister approved in Decision No. 827/QD-TTg the project to develop Vinh city, Nghe An province into an economic and cultural center of the North Central region, including the project "Building Phan Boi Chau High School for the Gifted into a high-quality key school" in accordance with the spirit of Resolution No. 26-NQ/TW of the Politburo .

Photo - My Ha (4)
Construction of the dormitory building in phase 2 of the project. Photo: My Ha

With the above special meaning, the investment in the construction of the project: Building a new Phan Boi Chau High School for the Gifted is really necessary and appropriate. This is also the long-standing desire of generations of teachers and students of the school with the desire to have a spacious, modern school, with adequate conditions for classrooms, functional rooms, sports fields, training grounds, etc. to ensure standards, synchronization, modernity, on par with the region and the world, meeting the requirements of training talents and high-quality human resources in the period of international integration.

Since 2018, due to the implementation of the new Phan Boi Chau High School for the Gifted, the repair and upgrading of the old Phan Boi Chau High School for the Gifted at the current location of Truong Vinh Ward has received almost no investment. After many years of use, many items of the school have now degraded and do not meet the requirements of the new General Education Program.

phoi-canh(1).jpg
Perspective of new construction of Phan Boi Chau High School for the Gifted, Nghe An province.

Due to the above difficulties, speeding up the construction progress of the new Phan Boi Chau High School for the Gifted is extremely urgent. However, to complete and put into use, the project needs to complete all 3 phases. Of which, the most important thing is to promptly provide enough capital to implement the construction.

Through research at the Management Board of Investment Projects for Construction of Civil and Industrial Works of Nghe An Province, from the beginning of 2025, implementing the public investment plan, Nghe An Province has added 68 billion VND to implement phase 2. The remaining 30 billion VND, according to the plan, will be provided in 2026 to supplement construction capital in time.

Photo - My Ha (6)
Construction of the headquarters building in phase 2 of the project. Photo: My Ha

Regarding phase 3 of the project, according to the public investment plan, it will also be in the period 2026 - 2030, with a total investment capital of about 290 billion VND. In order for the project to finish as planned, the Provincial People's Committee is also requesting the Management Board of Investment Projects for Construction of Civil and Industrial Works of Nghe An Province to review the project and adjust some items to suit actual requirements.

Speaking to Nghe An Newspaper and Radio and Television, a representative of the Project Management Board also said: According to the plan, the project will be completed before 2030. However, if funding is provided soon, the project can speed up construction and will be put into operation ahead of schedule.

Source: https://baonghean.vn/khoi-dong-lai-du-an-xay-dung-truong-thpt-chuyen-phan-boi-chau-10312816.html


Comment (0)

No data
No data

Same tag

Same category

Beautiful sunrise over the seas of Vietnam
Traveling to "Miniature Sapa": Immerse yourself in the majestic and poetic beauty of Binh Lieu mountains and forests
Hanoi coffee shop turns into Europe, sprays artificial snow, attracts customers
The 'two-zero' life of people in the flooded area of ​​Khanh Hoa on the 5th day of flood prevention

Same author

Heritage

Figure

Enterprise

Thai stilt house - Where roots touch the sky

News

Political System

Destination

Product