Representatives of local authorities, EVNNPT and construction units performed the project implementation ceremony - Photo: EVNNPT
The 500 kV Bac Ninh Transformer Station (TSS) and connecting line project is a special-class, group B energy project invested by EVNNPT, managed and operated by NPMB, and operated by Power Transmission Company 1 after completion. The project is built in Chi Lang commune, Bac Ninh province.
The main scale of the project is to build a new 500kV Bac Ninh substation with a capacity of 1,800 MVA, including 2 transformers, each transformer is 900MVA. The 500kV side installs 4 feeders, the 220kV side installs equipment for 13 feeders.
Control, protection and measurement systems, communications and SCADA are equipped in accordance with EVN and EVNNPT regulations, complying with current standards and regulations.
The connection line section will build two new 500 kV lines, one circuit, about 0.31 km long (branch 1) and 0.49 km (branch 2) connecting on the existing 500/220 kV Bac Ninh 2 - Pho Noi line.
At the same time, build two new 220 kV lines, two circuits, about 0.38 km long (branch 1) and 0.23 km (branch 2) connecting on the existing 500/220 kV Bac Ninh 2 - Pho Noi line.
Once completed, the project will meet the electricity supply needs of urban areas, industrial parks of Bac Ninh province and other loads in the region to promote economic development and improve social security in the locality.
EVNNPT representative said: Bac Ninh is a locality with rapid economic growth and a huge demand for electricity. Therefore, EVNNPT invested in the project to ensure electricity supply for the province as well as ensure regional energy security.
EVNNPT representative requested relevant units during the construction process to strictly implement technical regulations, construction procedures, ensure labor safety, environmental sanitation and construction quality. At the same time, it is necessary to strengthen coordination, mobilize maximum resources to speed up progress, complete energization according to the investor's direction.
EVNNPT leaders also expressed their deep gratitude to the government and people of Chi Lang commune, Bac Ninh province for accompanying and supporting the site clearance work, creating favorable conditions for the project implementation process. Affirming that the consensus of the people is an important foundation for the success of the project, at the same time wishing to continue to receive support and cooperation from all levels of government and people in the next construction phase.
As the investor, EVNNPT commits to implementing the project on schedule, with quality and absolute safety, closely coordinating with the locality in compensation and site clearance, ensuring the legitimate rights of the people. EVNNPT will also mobilize all resources, human resources, and synchronous coordination between the Project Management Board and contractors to put the project into operation as soon as possible.

Immediately after the launching ceremony, construction units immediately started leveling the project site - Photo: EVNNPT
The contractor representative pledged to focus resources on construction on schedule and quality, and hoped to continue receiving support and close coordination from the authorities and people in the areas the project passes through, especially in site clearance, to ensure stable electricity supply progress for the area.
Toan Thang