The Bac Ninh 500kV Transformer Station and Connection Line Project is a special-grade, Group B energy project invested by EVNNPT, managed and operated by NPMB, and operated by Power Transmission Company 1 after completion. The project is built in Chi Lang commune, Bac Ninh province.
The main scale of the project is to build a new 500kV Bac Ninh transformer station with a capacity of 1,800 MVA, including 2 transformers, each transformer is 900 MVA. The 500kV side installs 4 feeders, the 220kV side installs equipment for 13 bays. The control, protection and measurement, communication and SCADA (Supervision, Control and Data Acquisition) systems are equipped in accordance with the regulations of Vietnam Electricity (EVN), EVNNPT, and comply with current standards and regulations.
The connection line section will construct two new 500kV lines, one circuit, about 0.31 km long (branch 1) and 0.49 km (branch 2) connecting on the existing 500/220kV Bac Ninh 2 - Pho Noi line; construct two new 220kV lines, two circuits, about 0.38 km long (branch 1) and 0.23 km (branch 2) connecting on the existing 500/220kV Bac Ninh 2 - Pho Noi line.
Once completed, the project will meet the electricity supply needs of urban areas, industrial parks of Bac Ninh province and other loads in the region to promote economic development and improve social security in the locality.
EVNNPT representative said that Bac Ninh is a locality with rapid economic growth and huge demand for electricity. Therefore, EVNNPT invested in the project to ensure electricity supply for the province as well as ensure regional energy security.
EVNNPT representative requested relevant units during the construction process to strictly implement technical regulations, construction procedures, ensure labor safety, environmental sanitation and construction quality. At the same time, it is necessary to strengthen coordination, mobilize maximum resources to speed up progress, complete energization according to the investor's direction.
EVNNPT leaders affirmed that people's consensus is an important foundation for the project's success, and at the same time hope to continue receiving support and cooperation from all levels of government and people in the next construction phase.
As the investor, EVNNPT commits to implementing the project on schedule, with quality and absolute safety, closely coordinating with the locality in compensation and site clearance, ensuring legitimate rights for the people.
EVNNPT will also mobilize all resources, human resources, and synchronous coordination between the Project Management Board and contractors to put the project into operation as soon as possible.
The contractor representative pledged to focus resources on construction on schedule and quality, and hoped to continue receiving support and close coordination from the authorities and people in the areas the project passes through, especially in site clearance, to ensure stable electricity supply progress for the area.