The Government Office has just issued Official Dispatch No. 7310/VPCP-CN on urgently reviewing and removing difficulties and obstacles related to 4 key traffic projects scheduled to be completed in 2025 under Inspection Team No. 1.
According to the set schedule, the four North-South expressway projects of Hoa Lien - Tuy Loan, Quang Ngai - Hoai Nhon, Hoai Nhon - Quy Nhon and Quy Nhon - Chi Thanh sections under Inspection Team No. 1 will have about 86.47/231.27 km of technical traffic opened on August 19, 2025.
By the end of September 2025, about 114.7 km will be technically opened to traffic and the remaining 30.1 km will be completed in December 2025.
Deputy Prime Minister Nguyen Hoa Binh inspected the Hoa Lien - Tuy Loan Expressway Project in March 2025. |
To ensure the progress of project completion, Deputy Prime Minister Nguyen Hoa Binh - Head of Inspection Team No. 1 requested the localities of Da Nang, Quang Ngai, Gia Lai, Dak Lak to mobilize authorities and functional agencies to organize construction protection at locations and sections of roads that have been handed over; continue to organize construction protection according to the contractor's plan.
At the same time, organize dialogues and propaganda to get people to agree and support compensation policies according to regulations and commitments to compensation and support from investors and construction contractors.
Deputy Prime Minister Nguyen Hoa Binh also requested continued attention and drastic direction to functional agencies and local authorities at all levels to focus on thoroughly resolving difficulties and problems related to compensation and resettlement work before August 15, 2025...
The 4 expressway projects include: Hoa Lien - Tuy Loan, Quang Ngai - Hoai Nhon, Hoai Nhon - Quy Nhon and Quy Nhon - Chi Thanh sections, belonging to the North - South Eastern expressway with a total length of 4 routes of 231.27 km. The total investment is 49,786.385 billion VND. The total volume of site clearance is 1,327.54 ha/12,385 households, of which 3,264 households are resettled; 74 resettlement areas are built...
These highway projects are being accelerated to ensure full completion by 2025.
Source: https://baodautu.vn/chinh-phu-yeu-cau-khan-truong-hoan-thanh-4-du-an-cao-toc-trong-diem-qua-mien-trung-d352709.html