[Photo series] 1.8 thousand day journey from vast rubber plantations, villages to 'super' Long Thanh International Airport

(DN) - From the time the project started on January 5, 2021 until now, after nearly 5 years with nearly 1,800 days of construction, Long Thanh International Airport Phase 1 is gradually "reaching the finish line". From the vast rubber forests and villages, the shape of a "super" airport, a project symbolizing the country's development aspirations has taken shape.

Báo Đồng NaiBáo Đồng Nai19/11/2025

In 2020, Dong Nai province officially handed over land to relevant units to "start" the construction of Long Thanh Airport. Photo: Pham Tung
Along with the process of handing over land for construction, the site clearance work for the project area is being carried out in parallel. In particular, the site clearance for the rubber land area is being carried out first. Photo: Pham Tung
People in the project area demolished their houses and "gave up land" to build Long Thanh Airport. Photo: Contributor
Long Thanh Airport is invested and built on an area of ​​about 5,000 hectares, located in 6 communes of the old Long Thanh district, Dong Nai province. Photo: Contributor
Among the 6 communes in the Long Thanh Airport construction area, Suoi Trau commune was dissolved because most of its area was located in the airport construction area. Part of the remaining area of ​​the commune was merged into Bau Can commune, old Long Thanh district, Dong Nai province. Photo: Pham Tung
Suoi Trau Primary School in 2020. Photo: Pham Tung
At the end of 2020, Dong Nai province completed site clearance for a large part of the land area to build Long Thanh Airport. Photo: Contributor
Immediately after the site was handed over, Vietnam Airports Corporation (ACV) started the construction of the site leveling and drainage package. Photo: Pham Tung
Thousands of workers and machines were mobilized to level the ground for construction. The Long Thanh Airport Project site became the largest construction site in the country at that time. Photo: Pham Tung
At the end of August 2023, the construction of the passenger terminal - the "heart" of Long Thanh Airport phase 1 - began. Photo: Contributor
The passenger terminal construction is the most important item of the Long Thanh Airport Project Phase 1. The contract for construction and installation of passenger terminal equipment is worth 35 trillion VND. Photo: Pham Tung
The air traffic control tower project - the "brain" of Long Thanh Airport - will also be built in 2023. Photo: Contributor
To meet the requirements of shortening construction time and completing the project early, during the construction process, the Long Thanh Airport Project construction site is always lit up at night to carry out "3 shifts, 4 shifts", "working day and night". Photo: Pham Tung
After nearly 5 years of construction with nearly 1,800 days, tens of thousands of engineers, workers, laborers and machines and equipment worked with the spirit of "overcoming the sun, overcoming the rain, not losing to the storm"; "working through holidays and Tet" to complete the project early. Photo: Pham Tung
According to the plan, Long Thanh Airport Phase 1 will be officially inaugurated on December 19, 2025 and put into commercial operation in the first half of 2026. Photo: Pham Tung
According to plan, Long Thanh Airport phase 1 will be officially inaugurated on December 19, 2025 and put into commercial operation in the first half of 2026. Photo: Pham Tung
A series of headquarters buildings for state management agencies have been basically completed to be ready to serve when Long Thanh Airport is put into operation. Photo: Pham Tung
Two traffic routes connecting Long Thanh Airport (T1, T2) have also basically completed construction to serve traffic connection for this "super" airport project.

Pham Tung (performed)

Source: https://baodongnai.com.vn/kinh-te/202511/chum-anh-hanh-trinh-18-ngan-ngay-tu-bat-ngan-cao-su-lang-mac-den-sieu-cang-hang-khong-quoc-te-long-thanh-a570c40/


Comment (0)

No data
No data

Same category

Feast your eyes on the beautiful scenery of Vietnam in Soobin's MV Muc Ha Vo Nhan
Coffee shops with early Christmas decorations make sales soar, attracting many young people
What is special about the island near the maritime border with China?
Hanoi is bustling with flower season 'calling winter' to the streets

Same author

Heritage

Figure

Enterprise

The restaurant under the fruitful grape garden in Ho Chi Minh City is causing a stir, customers travel long distances to check in

News

Political System

Destination

Product