The Decision clearly states that the investment policy is approved; at the same time, the investor of the Project is Saigon - Hai Phong Industrial Park Joint Stock Company.
The project scale is 652.73 hectares. The project is implemented in Truong Tho, Truong Thanh, An Tien, Bat Trang communes, An Lao district, Hai Phong city with an investment capital of 8,094.4 billion VND.
The Deputy Prime Minister requested the Ministry of Planning and Investment to take responsibility for the assigned contents of project investment policy appraisal and to perform state management of industrial parks in accordance with the provisions of the law on investment and relevant laws.
Relevant Ministries are responsible for the content of project investment policy appraisal within their functions and tasks according to the provisions of the law on investment and relevant laws.
Hai Phong City People's Committee is responsible for the truthfulness and accuracy of the information, reported data and appraisal contents according to the provisions of law; receiving opinions from the Ministries; organizing the development and implementation of plans for land recovery, compensation, support, resettlement, conversion of land use purposes, land lease to implement the project according to the provisions of the law on land, the law on cultivation and other relevant legal provisions, in accordance with the documents approved by competent authorities on the scale of area, location and progress of project implementation; ensuring that there are no disputes or complaints about the right to use the project site; supplementing the lost area of land for rice cultivation or increasing the efficiency of rice land use according to the provisions of Point b, Clause 4, Article 182 of the Land Law.
Hai Phong City People's Committee requires investors to: (i) during the project implementation process, if they discover minerals with a higher value than minerals used as common construction materials, they must report to the competent state agency for settlement in accordance with the provisions of the law on minerals; (ii) comply with the provisions of the Law on Environmental Protection, the Law on Dikes, the Law on Irrigation, the Law on Water Resources, the Law on Natural Disaster Prevention and Control and other relevant legal provisions, ensuring that the project implementation does not affect the safety of the dike, the management and operation of the irrigation system and drainage, and does not cause flooding in the surrounding area; (iii) coordinate in compensation, support, resettlement and investment in the construction of workers' housing, service works and public utilities for workers working in the industrial park.
Hai Phong City People's Committee inspects and determines that investors meet the conditions for land lease by the State, permission to change land use purpose at the time of land lease, permission to change land use purpose; closely monitors the progress of project implementation, the use of owner's capital contribution as committed to implement the project, and the satisfaction of all conditions for organizations when doing real estate business as prescribed in Point b, Point c, Clause 2, Article 9 of the Law on Real Estate Business and Clause 1, Article 5 of Decree No. 96/2024/ND-CP...
Saigon - Hai Phong Industrial Park Joint Stock Company (investor) is responsible before the law for the legality, accuracy and honesty of the contents of the project dossier and documents sent to competent state agencies; comply with the provisions of law in implementing the project according to the approved planning and investment policy; carry out investment in the construction of the Trang Due 3 industrial park infrastructure system according to the construction zoning plan approved by competent authorities.
Contribute sufficient equity capital to implement the project; use equity capital to implement the project in accordance with the commitment and comply with the provisions of the law on investment, the law on land, the law on real estate business and other relevant provisions of law; fully meet the conditions for organizations when doing real estate business as prescribed in Point b, Point c, Clause 2, Article 9 of the Law on Real Estate Business and Clause 1, Article 5 of Decree No. 96/2024/ND-CP...
Source: https://kinhtedothi.vn/hai-phong-dau-tu-xay-dung-ket-cau-ha-tang-kcn-trang-due-3-hai-phong.html