Deputy Minister Nguyen Viet Hung acknowledged the contractors' efforts in the hot weather. However, the remaining time for the Hoa Lien - Tuy Loan expressway project is not much, so the sections that are eligible for construction and have no more problems need to be quickly mobilized to the maximum to implement the construction, completing the main route before August 19.
Regarding the 500m section that people have not cooperated with construction, Deputy Minister Nguyen Viet Hung noted that the Ho Chi Minh Road Project Management Board needs to coordinate with the locality to listen to people's opinions, propose a reasonable compensation level to create consensus, and soon complete the project. If people have opinions, invite them to the ward or commune headquarters to discuss and reach an agreement. Do not let people have to stay on duty at the highway construction site, which is hot and sunny, causing disorder, traffic safety and affecting the construction progress.
According to the report of the Ho Chi Minh Road Project Management Board, up to now, the construction value of the Hoa Lien - Tuy Loan expressway project has reached more than 502 billion VND, equivalent to 58.44% of the total investment and is entering the peak of completion.
At the construction site, 20 construction teams are being deployed, machinery and human resources are working continuously in 3 shifts per day to carry out the items of crushed stone, asphalt concrete, traffic infrastructure, residential underpasses, service roads, etc. Currently, contractors are focusing on the main road surface, if the weather is favorable, the entire road surface will be completed on August 15 and open to traffic on August 19.
However, the project still has some major problems. About 100m of the route cannot be constructed due to incomplete site clearance, and 9 land records are stuck. In Ba Na commune, many households reported that their houses were cracked due to vibration during construction, leading to the construction of a 500m long section of the road being prevented.

Faced with this situation, the Project Management Board has coordinated with the contractor and the insurance company to pay the third support payment to the affected people. At the same time, the Deputy Minister is requested to consult with the leaders of the Da Nang City People's Committee to direct relevant units to thoroughly handle the situation and hand over the entire clean site before July 20.
The Ho Chi Minh Road Project Management Board also proposed that Ba Na commune step up propaganda and mobilization to encourage people to cooperate, create favorable conditions for construction work, and ensure technical traffic progress. In addition, it recommended that the Ministry of Construction direct the acceleration of investment procedures for the next two resettlement areas, and promptly disburse capital for site clearance.
Source: https://www.sggp.org.vn/duong-cao-toc-hoa-lien-tuy-loan-con-vuong-mat-bang-du-kien-thong-tuyen-ngay-19-8-post804184.html