Great effort
The coastal route Nghi Son (Thanh Hoa) - Cua Lo ( Nghe An ) from Km7 to Km76 is a national key traffic project. With a total investment of more than 4,651 billion VND, the route is designed according to the level III plain standards, the roadbed is 12m wide, the road surface is 11m wide.
This project is divided into 2 packages, of which, package XL01 is implemented from Km7+00 to Km48+250; package XL02 is implemented from Km48+250 to Km76+00. The whole project has 8 bridges spanning river mouths and canals. Of which, there are 5 large bridges: Hoang Mai, Lach Quen, Cua Thoi, Lach Van, Nghi Quang and 3 small bridges: Tan Long, Nha Le canal, Nghi Tan.
.jpg)
Construction began in February 2022 and is expected to be completed in early 2026. Once completed, the route promises to be an important driving force for local economic development. In particular, the project will facilitate the connection of key economic zones in the region from Thanh Hoa to Nghe An; connecting Vissai International Seaport, Cua Lo Port, DKC Port and key tourist areas located along coastal localities, contributing to improving local competitiveness.
In addition to its economic significance, the route also plays a special role in ensuring national defense and security, creating favorable conditions for force mobilization and rapid response to emergency situations. At the same time, the route is also an important landscape axis, promoting the development of coastal tourism , opening up new spaces for coastal tourist cities in Nghe An.
According to the report of Nghe An Department of Construction, as of August 2025, the XL01 and XL02 packages have completed more than 91% of the volume. The project has also been allocated a capital of 4,037.6 billion VND, of which 435.9 billion VND will be allocated in 2025. The entire 56 km route of roadbed, road foundation, and asphalt has been basically completed; large and small bridges have been completed.
In particular, implementing the direction of the Provincial People's Committee, construction units are making every effort, determined to shorten the progress, mobilize maximum human resources and machinery, and continuously construct, striving to basically complete all items by the end of 2025 and early 2026, to put the project into operation, serving local socio-economic development.

Create consensus, remove bottlenecks in land clearance
In addition to the positive results in construction progress, the site clearance work of this project has also been actively resolved by the localities, especially in areas with problems. Up to now, the entire route has been handed over, reaching more than 99%. There are only 2 households in Tan Mai ward (belonging to the old Hoang Mai town), and Quynh Phu commune (belonging to the old Quynh Luu district), which are being actively mobilized by the local authorities to hand over the site soon.
Specifically, in Tan Mai ward, there is still Mr. Tran Van Danh's household in Son Long village (formerly Quynh Lap commune). It is known that the land area recovered from Mr. Danh's family belongs to plot number 156, map sheet number 23, with an area of 1,669.2m2 , which is residential land and land for growing annual crops. Although Mr. Danh's family has received compensation for 200m2 of residential land, they have not received compensation for the remaining land for growing annual crops.

The local government, since the time Hoang Mai town was still in operation, has approved and paid many times, but Mr. Danh's family still does not agree with the relocation costs. At the same time, they petitioned about the origin of the land and requested compensation for the cold storage built on land for annual crops.
Ms. Nguyen Thi Huong - Chairman of Tan Mai Ward People's Committee said: Mr. Danh's petitions have been answered many times by the local authorities, however, the family still refuses to hand over the site. In order to hand over the site on time to the construction unit, the locality has now completed the enforcement plan and is waiting for approval from the competent authorities.
In Quynh Phu commune, the new locality was established on the basis of merging Thuan Long, Van Hai, Phu Nghia communes of Quynh Luu district (old). Although the new government apparatus has been in operation for less than 2 months, it has demonstrated a strong and synchronous spirit in the work of clearing land for this project.

In particular, immediately after receiving the task from the former Quynh Luu District People's Committee, the commune government proactively propagated, mobilized, and organized many direct dialogues to resolve problems with related households. Specifically, on the morning of August 5, 2025, Quynh Phu Commune People's Committee organized a dialogue with 2 households of Ms. Ho Thi Truong and Mr. Truong Dac Quy in Minh Son village (former Phu Nghia commune), these are households whose land is affected by the Coastal Road Project. Both families even filed a complaint with the Provincial People's Committee.

At the dialogue, thanks to persistent advocacy and thorough explanation of the concerns of the people, by August 14, 2025, both households agreed to hand over the site, creating favorable conditions for the construction unit to continue implementing the project.
Currently, in Quynh Phu commune, there is only one household, Mrs. Vu Thi Chat, in Thuan Loi village, who has not yet handed over the land. The area that Mrs. Vu Thi Chat is using belongs to plot 155, map 299, with an area of 269.4m2 , of which the area within the clearance area is 51.9m2 (located on the road's ditch). Currently, Quynh Phu commune People's Committee has also approved the agricultural land compensation plan for Mrs. Chat's family, however, the family has not yet agreed and requested support according to the price of garden land and residential land and 100% of the value of assets on the land.
Mr. Ho Van Thanh - Chairman of Quynh Phu Commune People's Committee said that the locality is continuing to propagate and mobilize, at the same time, completing the necessary procedures for Mrs. Chat's household to soon hand over the site, ensuring the overall progress of the project.

On August 11, Chairman of the Provincial People's Committee Le Hong Vinh also inspected and directed to speed up the construction progress of the coastal road. In particular, the Chairman of the Provincial People's Committee also emphasized that the remaining work, although not large in volume, is decisive to the completion of the entire route, especially the problems related to site clearance.
Therefore, the Chairman of the Provincial People's Committee requested localities to continue to strengthen dialogue, mobilize and persuade people to understand the meaning and importance of the project for socio-economic development and community life. In case all measures have been fully applied but consensus is still not reached, local authorities will resolutely handle the case in accordance with the provisions of law, ensuring timely completion, quality and safety.
It can be seen that early removal of the site clearance “bottleneck” not only helps the contractor to implement the closed construction of the entire route, but also saves costs, avoids wasting time and resources. More importantly, this is a prerequisite for the project to be completed on schedule, put into operation in time, and promote the proposed socio-economic efficiency.
Source: https://baonghean.vn/duong-ven-bien-nghi-son-cua-lo-don-luc-cho-chang-nuoc-rut-quyet-thao-nut-that-mat-bang-cuoi-cung-10305639.html
Comment (0)