Of the total transferred capital, the local budget capital is 696 billion VND, the remaining 773 billion VND is from the central budget capital.

According to the Department of Finance, the reason why some projects have not fully disbursed capital is due to many obstacles in the implementation process, such as bauxite planning problems, slow site clearance, and limited construction capacity of some contractors.
Regarding the 669 billion VND of local budget that is slow to disburse, Binh Thuan (old) has 187.2 billion VND; Lam Dong (old) has 481.2 billion VND; Dak Nong (old) is 27.3 billion VND.

Regarding the central budget, projects that are unlikely to be fully disbursed in 2025 include: Dao Nghia - Quang Khe road (phase 2), Bao Loc - Lien Khuong highway, Tan Phu - Bao Loc highway, Ka Pet reservoir and DT.719B coastal axis (Hon Lan - Tan Hai section)...
Faced with the slow disbursement situation, the Investment and Construction Project Management Boards in Lam Dong have proposed that the Department of Finance advise the Provincial People's Committee to transfer all undisbursed capital sources to projects with high disbursement rates.
However, according to calculations, most of the local budget capital has been identified for projects that need additional capital. Of the 773 billion VND of central budget capital, Lam Dong province has proposed adjusting about 511 billion VND to 10 projects included in the investment plan but not yet allocated capital in 2025; the remaining amount of more than 266 billion VND will be returned to the central government according to regulations.

According to the People's Committee of Lam Dong province, the locality only prioritizes returning capital to projects that are stuck in mineral planning. Limiting the situation where it is impossible to disburse the money, the money is returned to the province and the Central Government.
Faced with the reality of having to repay capital, the Chairman of Lam Dong Provincial People's Committee requested the Department of Finance and related units to urgently coordinate and find effective solutions to optimally use capital resources to serve the socio -economic development goals of the locality.
Lam Dong's total public investment capital in 2025 is 18,600 billion VND. By the end of September 2025, the whole province has disbursed 5,254 billion VND, reaching 28.2% of the plan.