On the afternoon of November 18, Deputy Secretary of the Provincial Party Committee, Chairman of the Lam Dong Provincial People's Committee Ho Van Muoi chaired an online meeting with localities on the disbursement of public investment capital to date and the remaining tasks and solutions for 2025. Vice Chairmen of the Provincial People's Committee and leaders of departments and branches attended.

At the meeting, Chairman of Lam Dong Provincial People's Committee Ho Van Muoi directed that there is not much time left in 2025. From now on, the Provincial People's Committee will launch a 42-day, night campaign to speed up, speed up and even speed up in disbursing public investment capital.
We do not count Saturdays, Sundays, days and nights, determined and devoted to this work. The leaders of the Provincial People's Committee, departments and branches will be present directly, accompanying the units and localities, promptly resolving difficulties during the implementation process.
Chairman of Lam Dong Provincial People's Committee Ho Van Muoi

At the meeting, investors reported on progress, difficulties and obstacles in the process of disbursing public investment capital. Many solutions to promote the disbursement rate in the coming time were also proposed by investors, departments and branches.
Regarding capital disbursement, Director of Construction Investment Project Management Board No. 3, Ha Sy Son informed that by November 14, 2025, the unit's disbursement rate reached over 26.67%. It is expected that 10 projects of the unit and regional boards will request capital transfer to 2026. The remaining projects, the Project Management Board strives to complete in 2025.
“Land clearance is still the biggest bottleneck in project implementation. We are working with localities to speed up this area. The Board has made detailed plans for each project and assigned tasks to each individual during the implementation process. By the end of 2026, the Board's disbursement rate is expected to reach 74%,” Mr. Son pledged.

Reporting on the progress of the projects, Director of the Construction Investment Project Management Board No. 1, Nguyen Nhan Ban, informed that the unit has only disbursed 21.5% of the plan. Currently, the Board has worked resolutely with contractors, localities, and consulting units on site clearance. The difficulties and problems encountered have been basically resolved so far. "We have worked and made clear commitments with the construction units. If the weather is favorable, we will focus human and material resources to speed up the project's progress," said Mr. Ban.

Regarding the solution to promote the disbursement of public investment capital, Director of the Department of Construction Le Ngoc Tien proposed that local authorities should accelerate the determination of land prices and resettlement unit prices. This is the basis for compensation for site clearance. Once the site is available, the project can be implemented quickly.
At the meeting, Vice Chairman of Lam Dong Provincial People's Committee Vo Ngoc Hiep affirmed that regarding the disbursement of public investment capital, the leaders of the Provincial People's Committee have done everything within their capabilities. The Provincial People's Committee requires investors, construction units, and localities to participate with real determination. Projects and works need to report progress daily to grasp and handle arising difficulties.

According to the report of the Department of Finance, as of November 14, 2025, Lam Dong has disbursed 6,333 billion VND in public investment capital, reaching 33.88% of the plan. There are many reasons for the slow disbursement of public investment capital.
First of all, the site clearance work in many projects is slow because of the lack of agreement with the people. The determination of land origin, counting, appraisal, approval of site clearance plans, and the establishment of specific land prices are still limited. Some investors are not really proactive in managing, supervising, and urging contractors to implement.

Many contractors are incompetent and do not arrange enough personnel and machinery according to the bidding documents. Meanwhile, investors are not really determined in handling responsibilities.
Concluding the meeting, Deputy Secretary of the Provincial Party Committee, Chairman of the Lam Dong Provincial People's Committee Ho Van Muoi affirmed that, up to this point, the difficulties in disbursing public investment capital have been basically resolved. Mechanisms and institutions have been completed, except for projects stuck in bauxite planning. The biggest fault of slow capital disbursement is the lack of determination and determination.

There are only 42 days and nights left until the end of 2025. This is also the final time to race to innovate, correct errors and complete the target of disbursing public investment capital. The Provincial People's Committee has implemented all the solutions. The important issue is whether we are determined and resolute or not.
Chairman of Lam Dong Provincial People's Committee Ho Van Muoi
The Chairman of the Provincial People's Committee emphasized that there is no turning back in the disbursement of public investment capital. Directors of units must take decisive action, "holding hands and showing work" right at the construction sites and projects to complete the assigned tasks.