Increasing the capacity of Tuy Hoa 220kV transformer station, enhancing power security for Dak Lak province

(Chinhphu.vn) - The National Power Transmission Corporation (EVNNPT), the Power Transmission Project Management Board (NPTPMB) coordinated with relevant units to successfully energize the AT2 transformer with a capacity of 250MVA under the project "Increasing the capacity of Tuy Hoa 220kV Transformer Station from (2x125MVA) to (125+250MVA)".

Báo Chính PhủBáo Chính Phủ28/07/2025

Nâng công suất trạm biến áp 220kV Tuy Hòa, tăng cường đảm bảo điện cho tỉnh Đắk Lắk- Ảnh 1.

Panorama of Tuy Hoa 220kV Substation - Photo: EVNNPT

The project is implemented at the 220kV Tuy Hoa Transformer Station (TSS), Phu Hoa 2 Commune, Dak Lak Province, with EVNNPT as the investor, NPTPMB on behalf of the investor manages and operates the project, and Power Transmission Company 3 (PTC3) takes over the operation.

After nearly 10 months of urgent construction, the project was completed ahead of schedule, ensuring quality, technique and labor safety.

The project has the scale of replacing the existing AT2 transformer (125MVA) with a new transformer with a capacity of 250MVA; installing a new 110kV feeder to the 110kV An My substation (E02); expanding the busbar system and synchronously upgrading auxiliary equipment to match the upgraded transformer capacity. At the same time, the project also completes the control - protection system, fire protection misting system and upgrades the infrastructure for long-term operation.

The completion of the AT2-250MVA transformer and 170 bay will contribute to increasing the power supply capacity, meeting the increasing load demand in the South Central region, especially Phu Yen and neighboring provinces.

The project is also important in improving the reliability, safety and stability of the regional transmission grid, creating favorable conditions for collecting renewable energy sources.

The project was completed on the 96th anniversary of the founding of the Vietnam Trade Union (July 28, 1929 - July 28, 2025) and to welcome the 4th Congress of Delegates of the Vietnam Electricity Group Party Committee, term 2025 - 2030, making it even more meaningful.

The success of the project is the result of close direction from EVNNPT, close coordination between contractors, construction units, consultants, supervisors and active support from local authorities.

Toan Thang


Source: https://baochinhphu.vn/nang-cong-suat-tram-bien-ap-220kv-tuy-hoa-tang-cuong-dam-bao-dien-cho-tinh-dak-lak-102250728160116309.htm


Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product