Speeding up on the construction site of Lang Nu residential area

Việt NamViệt Nam29/10/2024


After completing the installation of concrete pillars, the first stilt houses began to be roofed. A team of 20 people was in charge of the work, which required speed, precision, and ensuring technical and aesthetic requirements.

On average, it takes 1 day to roof each house.

Mr. Pham Chi Cong, Head of the Mechanical Team, Army Corps 12, Truong Son Construction Corporation shared: “The trusses are processed underground, then lifted up to the roof using a crane, and purlins are used to run around. Paint 3 coats, 1 coat of anti-rust paint, 2 coats of color paint. Making imitation tile roofing has many difficult steps, requiring higher techniques than regular roofing.”

On average, each house will take 1 day to roof. After completion, the units will start painting, doing electricity and water, interior decoration. It is expected that from digging the foundation to completing a stilt house will take from 20 to 30 days.

Materials are continuously transported here to ensure the construction process at different stages.

Materials are continuously transported here to ensure the construction process at different stages. At this time, the 12th Corps has increased to 260 people working in 3 continuous shifts. From pouring foundation pillars, assembling house frames, roofing, painting to finishing the interior. Each group takes on a different part of the work and performs it in parallel to ensure progress. The changing landscape every day is the feeling of many people when witnessing the construction speed at the construction site.

The landscape changes every day is the feeling of many people when witnessing the construction speed at the construction site.

Ms. Hoang Thi Dat, Lang Nu village, Phuc Khanh commune, Bao Yen district shared: "Coming here and seeing this makes me so excited. People work day and night like this, it's beautiful and makes me so happy."

Corps 12 strives to complete 40 houses, a school, a cultural house and traffic infrastructure in Lang Nu residential area by December 22, 2024.

To date, the construction unit has completed the foundation of 28 houses, of which 15 houses have had their frames erected and 5 houses are being roofed. Corps 12 is striving to complete all 40 houses, along with a school, a cultural house and traffic infrastructure in Lang Nu residential area by December 22, 2024, to welcome residents to settle down.

Trung Kien - Focus


Source

Comment (0)

No data
No data

Same category

DIFF 2025 - An explosive boost for Da Nang's summer tourism season
Follow the sun
The majestic cave arc in Tu Lan
The plateau 300km from Hanoi has a sea of ​​clouds, waterfalls, and bustling visitors.

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product