Working with the EVN delegation on Lai Chau province side were comrades: Le Van Luong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee; Giang A Tinh - Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee and leaders of relevant departments and branches.
Working scene.
At the meeting, EVN representatives reported on the situation of electricity supply and investment in construction of power projects in Lai Chau province. Accordingly, the current status of power sources, grids and electricity consumption in the province; regarding power sources: the total capacity of hydropower sources operating in Lai Chau province is 3,135 MW including Lai Chau Hydropower Plant - 1,200 MW, Ban Chat Hydropower Plant - 220 MW, Huoi Quang Hydropower Plant (520 MW) and other medium and small hydropower plants with a total capacity of about 1,195 MW connected to the distribution grid. In addition, there are about 150 MW of small hydropower plants in Yen Bai and Lao Cai areas generating power to the system via the Lai Chau grid.
ENV representative approved the report.
The 110kV grid has 4 110kV transformer stations with a total capacity of 157 MVA belonging to the electricity company, with the nature of the load consumption being much lower than the total capacity of the hydropower plants connected to the distribution grid, the 110kV lines mainly transmit the capacity of the hydropower plants... Commercial electricity, the average growth in the period 2021-2024 is 7.89%/year. In 2024 alone, commercial electricity will reach 267.82 t.kWh, an increase of 5.2% over the same period... EVN representative presented the investment plan and the necessity of expanding hydropower plants and developing solar power projects on lakes. EVN proposed to invest in 04 floating solar power projects on hydropower reservoirs with a total capacity of 462MWp/420MW and 03 hydropower plant expansion projects with a total capacity of 770MW including: Lai Chau Hydropower Plant expansion 400MW; Ban Chat Hydropower Plant expansion 110MW; Huoi Quang Hydropower Plant expansion 260MW...
Comrade Nguyen Anh Tuan - General Director of EVN spoke about the necessity of implementing the projects.
EVN requested the People's Committee of Lai Chau province to continue to facilitate and support EVN and its member units in investing in the construction of power source and grid projects, and power supply in the province; the Provincial People's Committee considered adding and updating power source projects proposed by EVN to the province's planning, including recommending to accelerate the investment progress of floating solar power projects on the reservoirs of Lai Chau, Huoi Quang, and Ban Chat hydropower plants in the 2025-2030 period. The Provincial People's Committee directed departments and branches to approve EVN to carry out project surveys; guide EVN in submitting and approving investment policies, and at the same time approving EVN as the investor to soon implement the investment...
Comrade Giang A Tinh - Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee spoke at the meeting.
Discussing at the working session, members of the EVN delegation and leaders of departments and branches of Lai Chau province agreed with the implementation of floating solar power projects on hydropower reservoirs and the expansion of hydropower plants. The units will proactively connect so that the steps can be implemented quickly and effectively; To release the capacity of power grid development projects in the area, EVN needs to speed up the progress of the 220kV Pac Ma - Muong Te project and a number of other projects...
The leaders of the Department of Industry and Trade agreed to implement the projects.
Speaking at the meeting, Mr. Le Van Luong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee expressed his gratitude for EVN's support to the province. The Lai Chau Provincial People's Committee will establish working groups to support compensation and site clearance for EVN's energy development projects in the area with the participation of provincial departments, branches and sectors. The Provincial People's Committee agrees with the policy of developing solar power and projects to expand 3 hydropower plants. The Provincial People's Committee will coordinate to implement the steps to adjust the planning.
Comrade Le Van Luong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee spoke at the meeting.
The Chairman of Lai Chau Provincial People's Committee requested that EVN soon have specific information to coordinate with localities to adjust the planning. EVN units need to have a focal point to synthesize and report related issues to Lai Chau Provincial People's Committee. Coordinate with localities to carry out well the survey and planning of projects that need to ensure environmental landscape and tourism development. Currently, Lai Chau still has 8 villages without electricity; EVN is expected to pay attention to investing in providing electricity to these villages. EVN is studying to have sources of livelihood support for households resettled by EVN's hydropower projects in the area. EVN is considering accompanying the program to eliminate temporary and dilapidated houses in the province.
Source: https://baolaichau.vn/kinh-te/tap-doan-dien-luc-viet-nam-lam-viec-voi-ubnd-tinh-lai-chau-1371685