Phase 2 of the Vu Cong Dan road renovation and expansion project, connecting Hai Duong City with Cam Giang and Binh Giang districts, requires the acquisition of 74 land plots belonging to 68 households.
To date, authorities have approved compensation and support plans for 56 households, of which payments have been made to 45 households. Eleven households have had their compensation and support plans approved but have not yet received the money or handed over the land.

The People's Committee of Hai Duong City has assigned the People's Committee of Tu Minh Ward to disseminate information and encourage households to accept compensation and hand over the land; at the same time, to finalize the compensation and support plan for the remaining households according to regulations.
The People's Committee of Hai Duong City is striving to complete the land clearance for the project before April 20th.
The Vu Cong Dan road renovation and expansion project has a total investment of 1,042 billion VND, with a length of over 1.6 km and a width of 33 m. This is a key project implementing the Resolution of the City Party Congress for the 2020-2025 term.
The project is divided into two phases for land clearance. Hai Duong City has completed land clearance and handed over the land to the construction unit for Line 1, and is currently clearing land for Line 2.
PVSource: https://baohaiduong.vn/tp-hai-duong-phan-dau-giai-phong-xong-mat-bang-du-an-duong-vu-cong-dan-giai-doan-2-truoc-20-4-408981.html