Receiving and participating in the working delegation from Dong Nai province was Vice Chairman of the Provincial People's Committee Ho Van Ha.
Minister of Construction Tran Hong Minh inspects the construction progress of the Bien Hoa - Vung Tau Expressway Project. Photo: Pham Tung |
At the Bien Hoa - Vung Tau Expressway Project, the working group inspected the field at the intersection with the road to Long Thanh Airport, Tan Hiep intersection and some locations on the route.
According to Project Management Board 85, for Project Component 2, the construction output has reached 51%, many main construction items are following the schedule. However, the project's construction progress is still affected because at some locations, the relocation of technical infrastructure systems has not been completed.
Meanwhile, at Project Component 1, contractors are also accelerating construction by maintaining 34 construction sites. The project's two construction packages, package 18, accounted for more than 14% of total output and package 21 accounted for more than 48% of total output.
Minister of Construction Tran Hong Minh discussed with investors and contractors of Long Thanh Airport Project. Photo: Pham Tung |
According to Vice Chairman of the Provincial People's Committee Ho Van Ha, the province is currently urging relevant units to speed up the relocation of technical infrastructure systems to serve the construction of two component projects of the Bien Hoa - Vung Tau Expressway Project. Currently, Dong Nai has licensed enough land mines to serve the construction of the expressway.
Provincial leaders also regularly inspect, urge, and evaluate the actual situation at the scene day and night, especially the site clearance work. Recently, they have enforced a number of cases to hand over the site to the investor.
For Component Project 1 invested by Dong Nai province, two units met the construction requirements, the remaining units are still slow in construction.
Minister of Construction Tran Hong Minh presents gifts to encourage construction workers of Bien Hoa - Vung Tau Expressway Project. Photo: Pham Tung |
During the inspection, Minister of Construction Tran Hong Minh requested units to take advantage of favorable weather conditions during the dry season to speed up construction progress. Dong Nai province is interested in further accelerating the relocation of technical infrastructure systems.
Regarding project contractors, Minister Tran Hong Minh emphasized that if any unit is slow or does not meet requirements, it must be replaced to meet project progress.
Also at the inspection, Minister Tran Hong Minh gave gifts and encouraged the project construction forces.
Pham Tung
Source: https://baodongnai.com.vn/tin-moi/202505/bo-truong-bo-xay-dung-tran-hong-minh-thay-the-nha-thau-thi-cong-cham-khong-dat-yeu-cau-de-bao-dam-tien-do-du-an-duong-cao-toc-bien-hoa-vung-tau-02123c6/