Mr. Uong Viet Dung, Chief of Office of the Ministry of Transport , said that on the morning of April 29, the North-South Expressway Project, Mai Son - National Highway 45 and Phan Thiet - Dau Giay sections will be officially inaugurated and put into operation. However, the Ministry of Transport has not yet collected tolls on these routes.
Regarding the Vinh Hao - Phan Thiet expressway project, the Chief of Office of the Ministry of Transport said that it will be inaugurated and put into use on May 19. After the inauguration, the competent authority has not yet collected tolls on this expressway.
According to the Chief of Office of the Ministry of Transport, the three above-mentioned expressway sections were invested in and built using state budget capital.
To ensure funding for future key transport projects, the government will collect tolls on the above expressways. However, the National Assembly has only given the go-ahead for the government to develop a toll collection plan, and developing the plan and waiting for the National Assembly to approve it will take more time.
Therefore, the three expressway sections Mai Son - National Highway 45 and Phan Thiet - Dau Giay, Vinh Hao - Phan Thiet which are about to be put into operation will not collect tolls for vehicles passing through.
Previously, the Cao Bo - Mai Son expressway section of the North - South expressway project in the 2017-2020 period was inaugurated on February 4, 2022, but toll collection has not yet begun after more than a year of operation.
A section of Phan Thiet - Dau Giay highway through Dong Nai - Photo: Vinh Phu
Mai Son - National Highway 45 Expressway (part of the North - South Expressway Project Phase 1) with a total investment of more than 12,100 billion VND was started on September 30, 2020. The project has a total length of 63.37 km (14.35 km through Ninh Binh province; 49.02 km through Thanh Hoa province).
This project starts at Mai Son intersection, Yen Mo district (Ninh Binh) connecting with Cao Bo - Mai Son expressway and ends at Nghi Son - Tho Xuan road (in Tan Phuc commune, Nong Cong district, Thanh Hoa) connecting with National Highway 45 - Nghi Son expressway.
Mai Son - National Highway 45 Expressway is built with a scale of 6 lanes, 32.25 m roadbed, reaching a design speed of 120 km/h; the investment phase will build 4 limited lanes, 17 m roadbed, reaching a design speed of 80 km/h.
Once put into operation, the route will shorten travel time from Hanoi to Thanh Hoa to 2 hours, instead of the current 2.5 - 3 hours.
The Phan Thiet - Dau Giay Expressway is 99 km long, started in September 2020, has a scale of 6 times the number of vehicles, and a total investment of more than 12,500 billion VND. The starting point intersects with the Vinh Hao - Phan Thiet Expressway in Ham Thuan Nam District (Binh Thuan) and the ending point intersects with the Ho Chi Minh City - Long Thanh - Dau Giay Expressway in Thong Nhat District (Dong Nai). After its inauguration, the route will help shorten the travel time from Ho Chi Minh City to Phan Thiet City (Binh Thuan) from 5-6 hours to 2 hours.
Source