The working content revolved around resolving difficulties, problems, proposals and recommendations of Binh Phuoc Electricity Company related to power projects deployed in the province and recommendations on adjusting the 110kV power grid profile into the implementation plan of Binh Phuoc Provincial Planning for the period 2021-2030, with a vision to 2050.
Working scene
According to EVNSPC's report, in the 2016-2024 period, 15 110kV power grid projects/works in Binh Phuoc province have been completed with a total increase of 62,518km of lines and 618MVA of transformer stations; the projects being implemented in the 2024-2025 period are 12 categories with a total increase of 183MVA, 135,783km of lines and a total investment of 1,479.5 billion VND.
Regarding the proposed revision and adjustment of the Binh Phuoc Provincial Planning, after reviewing, EVNSPC has sent a document requesting the People's Committee of Binh Phuoc province to continue to consider and approve the revision and adjustment of the power supply network development plan under the provincial planning, and issue a plan to implement the provincial planning with a list including 8 projects that have started construction and 4 projects in the investment preparation stage. Thereby, it aims to ensure the progress of 110kV power grid projects implemented by EVNSPC in Binh Phuoc province, promptly serving the socio-economic development of the province.
Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee Le Truong Son spoke at the meeting.
EVNSPC Deputy General Director Doan Duc Hung hopes that the Provincial People's Committee will urge and direct supporting sectors to have a plan to quickly handle problems.
Delegates discuss at the meeting
At the meeting, the two sides discussed difficulties and problems related to investment in the construction of 110kV power projects in the province, including the request for approval of investment policies and compensation for site clearance. The two sides also discussed in detail the solutions to the problems, the adjustment and supplementation of planning, the location of adjustment, etc.
Speaking at the meeting, Vice Chairman of the Provincial People's Committee Le Truong Son affirmed that the province will consider and direct to accelerate the implementation of 110kV power grid projects/works. Regarding the update to the Provincial Planning, the two sides will coordinate to fully update. For the pillars that are stuck in the Bu Nho Urban Master Plan and the Bu Nho Commune Residential Area Planning, the Department of Industry and Trade will be assigned to preside over and work with departments, branches, Phu Rieng district and have a written report to the Provincial People's Committee.
Vice Chairman of the Provincial People's Committee Le Truong Son also gave specific instructions on other related contents, in order to promptly handle difficulties and problems to soon implement power grid projects and works.
Source: https://baobinhphuoc.com.vn/news/4/171437/day-nhanh-tien-do-thuc-hien-cac-du-an-cong-trinh-luoi-dien-110kv