According to local leaders, the land acquisition dossiers for the expressway project are still slow. Currently, nearly 350 households have agreed to hand over their land for the project.
On March 11, according to Giao Thong Newspaper reporters, the authorities in Bien Hoa City ( Dong Nai ) are continuing to propagate and mobilize people to hand over land in Phuoc Tan Ward and Tam Phuoc Ward. Currently, nearly 350 households have agreed to hand over land, dismantle construction works and hand over land to the project.
The first section of Bien Hoa - Vung Tau Expressway has a more favorable basic surface than 1 month ago.
Of these, 170 households in Tam Phuoc ward agreed to hand over the land, only 7 households are subject to forced eviction.
In Phuoc Tan ward, there are still many households that have not agreed to hand over the land. These cases, after review, are mostly households that bought land with handwritten papers and illegally built houses on agricultural land that are subject to compulsory enforcement.
Mr. Ho Van Nam, Secretary of Bien Hoa City Party Committee, said that there is a delay in processing the files of forced land handover. Up to now, the number of forced files that the Provincial Land Fund Development Center has carried out according to the procedures to transfer to the City People's Committee to sign the forced decision is slow in time and small in number.
Among more than 40 files sent to Bien Hoa City People's Committee, many files do not have enough content according to regulations so they must be returned for additional information to prolong the time. Currently, Bien Hoa City People's Committee has only signed the decision to enforce 7 more cases, expected to be implemented on March 13.
Faced with this delay, Bien Hoa city leaders requested the Provincial Land Fund Development Center to mobilize staff and specialists in charge of professional matters to review and consolidate all files that have not yet handed over the site to put them under enforcement, determined to hand over the site in March.
Bien Hoa - Vung Tau Expressway Phase 1 has a total project length of about 53.7km. Of which, the section passing through Dong Nai province is about 34.2km; Ba Ria - Vung Tau province is about 19.5km.
Phase 1 scale is from 4-6 lanes, the completed expansion phase ensures the scale of 6-8 lanes. Preliminary total investment is 17,837 billion VND.
Currently, the progress of component 1 and component 2 projects through Dong Nai is only over 20-30% of output. The section through Ba Ria - Vung Tau alone is over 74%.
Source: https://www.baogiaothong.vn/gan-350-ho-dan-dong-thuan-ban-giao-mat-bang-cao-toc-bien-hoa-vung-tau-192250311180134931.htm