Hai Phong and Hai Duong speed up disbursement of public investment capital

In the first 5 months of 2025, the disbursement rate of public investment capital in Hai Phong and Hai Duong has improved significantly.

Báo Đầu tưBáo Đầu tư29/12/2024

In Hai Phong City, according to the report of the Ministry of Finance , as of May 31, 2025, the disbursement of public investment capital reached 7,500 billion VND, equal to 29.48% of the plan assigned by the Prime Minister. Of which, the disbursed central budget capital was 459,245 billion VND, reaching 100%; the city budget capital disbursed nearly 7,040,755 billion VND, reaching 28.18% of the plan.

Thus, in May 2025 alone, the City accelerated the disbursement of additional investment capital by more than VND 3,300 billion (the figure as of April 30, 2025 was VND 4,197 billion, equal to 16.5% of the plan assigned by the Prime Minister ).

In the 2025 public investment capital plan, the City allocates more than VND 16,400.1 billion to invest in projects and works for 29 project investors to complete the transport, urban and regional infrastructure systems and promote growth.

In Directive No. 43-CT/TU on strengthening leadership, direction, striving to complete and exceed the target of state budget revenue, public investment disbursement and economic growth of the City in 2025, the Standing Committee of Hai Phong City Party Committee requested localities and investors of public investment projects in the area to focus on project implementation and public investment disbursement in 2025. The rate of public investment disbursement is guaranteed to reach 15% by the end of the first quarter of 2025 (completed), 40% by the end of the second quarter of 2025 (29.48% by the end of May 2025), 70% by the end of the third quarter of 2025, 90% by December 31, 2025 and 96% by January 31, 2026.

According to Mr. Nguyen Ngoc Tu, Director of Hai Phong Department of Finance, to ensure the disbursement progress according to the direction of the Standing Committee of the City Party Committee, project investors must speed up the construction progress of works and projects. Along with the efforts of investors and contractors, there needs to be close coordination between departments, branches and localities in removing obstacles and speeding up the progress of site clearance for projects. Units need to focus maximum resources on compensation, site clearance, and handover of land funds for project implementation, especially key projects of the City.

Meanwhile, Hai Duong province disbursed more than VND 4,200 billion in public investment capital in the first 5 months of 2025, reaching 37.4% of the plan assigned by the province, 40.7% of the plan assigned by the Prime Minister, higher than the national average (the national average reached 22.2%) and exceeding 0.4% compared to the 2025 scenario plan of the Provincial People's Committee.

Some projects with high disbursement rates include: Renovation and upgrading of Road 395 (section from km16+750 - km23+920) and the approach road to Cay bridge, bypass road through Long Xuyen residential area (Binh Giang), reaching 94.4% of the total investment; Construction of Kinh Mon river overpass and approach road connecting the interchange with National Highway 5, reaching 57.3%; Investment in construction of interchange connecting National Highway 17B with National Highway 5, Hanoi - Hai Phong railway, reaching 48.3%; Investment in construction of road and Van bridge connecting National Highway 37 (Chi Linh city) with the approach road to Trieu bridge (Kinh Mon town), reaching 37.4%...

According to Mr. Nguyen Trong Tue, Director of Hai Duong Department of Finance, the disbursement results in the first 5 months of the year in Hai Duong basically followed the plan and scenario, achieving a disbursement rate higher than the national average. However, according to Mr. Tue, it is necessary to continue to drastically accelerate public investment. In particular, doing a good job of investment preparation, completing site clearance before July 1...

According to the scenario, Hai Duong province strives to disburse 3,270 billion VND in the second quarter of 2025, reaching 50% of the annual plan; disburse 2,170 billion VND in the third quarter of 2025 (disbursement of 7,398 billion VND in 9 months), reaching 70.8% of the annual plan. Accumulated to October 2025, Hai Duong province disbursed 77%, November 2025 was 81%, December 2025 was 93%, January 2026 will disburse 99.7% of the total public investment capital.

Projects in the 2025 public investment plan are planned with specific progress, step by step implementation for each project with disbursement progress included in the software "Quanlydautucong.haiduong.info.vn". In the 2025 public investment plan, the province focuses on allocating from the budget a total of nearly 8,500 billion VND for 25 projects under construction (about 6,682 billion VND), 10 newly started projects (about 1,919 billion VND). At the same time, support the district level to implement a number of important key traffic projects connecting with Hai Phong, Quang Ninh, Hung Yen.

Source: https://baodautu.vn/hai-phong-hai-duong-tang-toc-giai-ngan-von-dau-tu-cong-d297515.html


Comment (0)

No data
No data

Same category

Discover the process of making the most expensive lotus tea in Hanoi
Admire the unique pagoda made from more than 30 tons of ceramic pieces in Ho Chi Minh City
Village on the mountain top in Yen Bai: Floating clouds, beautiful like a fairyland
Village hidden in the valley in Thanh Hoa attracts tourists to experience

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product