Fix before 27-12

Người Lao ĐộngNgười Lao Động21/12/2024

(NLDO) - The investor requested the contractor to quickly complete the work of repairing and fixing the unsecured patching locations on the Vinh Hao - Phan Thiet expressway.


On December 21, Project Management Board 7 (PMU 7), under the Ministry of Transport , responded to the information "The expressway worth more than 10,000 billion VND has been patched up unevenly without collecting tolls" reported by Nguoi Lao Dong Newspaper.

According to this unit, immediately after receiving feedback about the patching situation on the Vinh Hao - Phan Thiet expressway, the unit operating the Vinh Hao - Phan Thiet expressway project held a meeting with the contractor and related parties.

Vụ đường cao tốc hơn 10.000 tỉ dặm vá lởm chởm: Khắc phục trước ngày 27-12- Ảnh 1.

Patching points due to damaged road surface appeared in both directions North - South, South - North on Vinh Hao - Phan Thiet expressway, from Km 175 - Km 160

Project Management Board 7 said that the damage to the asphalt concrete pavement mentioned in the article was within the scope of construction by Phuc Loc Group Joint Stock Company, under Package XL03, the Vinh Hao - Phan Thiet section investment and construction component project.

Although Phuc Loc Group Joint Stock Company promptly repaired the damage, some locations have not yet met technical and aesthetic requirements. To avoid similar situations that cause public outrage and ensure traffic safety on the route, especially during the upcoming Tet holiday, Project Management Board 7 requests the unit to urgently carry out the repair.

In particular, urgently inspect, review the site and immediately repair and fix the repaired locations that do not meet technical and aesthetic requirements as well as other locations if there is a risk of future damage under the responsibility of the construction warranty across the entire scope constructed by the Contractor in Package XL03.

Vụ đường cao tốc hơn 10.000 tỉ dặm vá lởm chởm: Khắc phục trước ngày 27-12- Ảnh 2.

The road surface of Vinh Hao - Phan Thiet highway has some uneven patches.

The contractor is required to report the implementation plan to the Road Management Office IV.1, Project Management Board 7, and the supervision consultant for inspection, supervision, and to ensure completion of the remediation and repair work before December 27, 2024.

During the implementation process, the contractor must strictly comply with the approved traffic safety measures to ensure the safety of vehicles in circulation. The contractor is fully responsible before the Ministry of Transport and the law if traffic safety is violated.

Project Management Board 7 also requested the Supervision Consultant to inspect, urge and supervise the contractor's implementation process and required the contractor to strictly comply with the approved construction organization measures throughout the implementation process to ensure traffic safety.



Source: https://nld.com.vn/vu-duong-cao-toc-hon-10000-ti-dam-va-lom-chom-khac-phuc-truoc-ngay-27-12-196241221145144244.htm

Comment (0)

No data
No data

Same tag

Same category

Explore Phu Quoc primeval forest
View Ha Long Bay from above
Enjoy the top fireworks at the opening night of the 2025 Da Nang International Fireworks Festival
Da Nang International Fireworks Festival 2025 (DIFF 2025) is the longest in history

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product