Ho Chi Minh City Ring Road 3 (through old Binh Duong ) is one of the key projects that Ho Chi Minh City is urging to disburse - Photo: CHAU TUAN
This important content is in the conclusion of Vice Chairman of Ho Chi Minh City People's Committee Bui Xuan Cuong after the meeting on the disbursement of public investment capital in the first 10 months of 2025 (November 5), along with solutions to urge progress in the last months of the year.
Accordingly, the total public investment capital in 2025 of Ho Chi Minh City after the arrangement is 152,241 billion VND, reaching 128% of the capital level assigned by the Prime Minister (118,948 billion VND).
As of November 4, the city has disbursed 67,251 billion VND, reaching 56.5% of the plan assigned by the Prime Minister, higher than the national average (54.4%) and equal to 44.2% of the capital plan the city has deployed.
Of the 10 specialized project management boards under the Ho Chi Minh City People's Committee with a capital scale of more than 1,000 billion VND, 5 boards have a disbursement rate higher than the city's average, the remaining 5 boards are behind schedule. Of the 37 regional project management boards under the Department of Construction or Project Management Boards (under the Ho Chi Minh City People's Committee), 18 boards have good disbursement, 19 boards are slower than average.
To achieve the target of disbursing the entire 118,948 billion VND of capital assigned by the Prime Minister, Mr. Bui Xuan Cuong requested units to strictly implement the emulation campaign "100 days of streamlining - strong - effective, efficient, effective", considering disbursement as a particularly important political task, mobilizing the entire political system to work together, speeding up compensation and site clearance, not letting projects be delayed due to waiting for site clearance.
"Absolutely do not delay or interrupt work for the reason of arranging and organizing the apparatus, especially the rearrangement of the Land Fund Development Center ," the conclusion clearly stated.
The Vice Chairman of the Ho Chi Minh City People's Committee requested departments, agencies and investors to comply with the principle of "clear people, clear work, clear responsibility, clear authority, clear time, clear results". Investors must mobilize people and machines to work in 3 shifts, 4 shifts, adding at least 15 - 20% more volume than planned.
Within 4 working days from the date of completion of the volume, the acceptance and payment documents must be completed and sent to the State Treasury.
The Department of Construction was assigned to compile a list of 34 key projects registered for "3 shifts, 4 teams" construction, and quickly appraise and approve the remaining documents in November. The Department of Agriculture and Environment coordinated to ensure the source of construction materials, while the Department of Finance advised on adjusting the public investment plan before November 15.
For ODA projects with tax problems such as Ho Chi Minh City Environmental Sanitation - Phase 2 and Binh Duong Water Environment Improvement, investors are required to report and propose solutions before November 15.
In addition, Mr. Cuong also directed to focus on completing compensation and site clearance for large capital projects such as Ring Road 3 (Binh Duong area), Ring Road 4, Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway, Provincial Road 991 and river embankment projects, expanding key traffic routes, ensuring disbursement of all capital within the prescribed time limit.
Source: https://tuoitre.vn/tp-hcm-yeu-cau-tang-toc-de-giai-ngan-het-152-241-ti-dong-von-dau-tu-cong-nam-2025-20251113081906126.htm