Why is the hundred billion dong embankment road in Can Tho still dark despite having lights?

Báo Giao thôngBáo Giao thông01/07/2024


The Cai Son - Muong Khai canal renovation project includes two packages worth more than 300 billion VND, under the Can Tho City Development Project and Urban Resilience Enhancement Project (Project 3), invested by the Can Tho ODA Project Management Board.

Vì sao đường kè trăm tỷ ở Cần Thơ có đèn nhưng vẫn tối om?- Ảnh 1.

Darkness on the road behind the embankment on the right bank of Cai Son canal. Photo: Nguyen Viet.

The project started at the end of 2020 and was completed nearly two years ago, including embankments, railings, sidewalks and roads behind the embankment... on the right side of Cai Son canal.

The completion of the project has been the expectation of the people of Ninh Kieu and Binh Thuy districts for many years.

In addition to contributing to beautifying and creating urban landscapes, the project also puts an end to flooding during the rainy season and high tides on 5km of embankment on the right side of Cai Son canal.

However, although it has been completed for nearly two years, the street lighting system behind the embankment has been installed but people rarely see the street lights.

Vì sao đường kè trăm tỷ ở Cần Thơ có đèn nhưng vẫn tối om?- Ảnh 2.

The little light coming from the houses is not enough to light up the construction site that was completed nearly two years ago. Photo: Nguyen Viet.

Mr. Nguyen Van Khoa, a resident of Area 4, An Binh Ward, Ninh Kieu District, said: "The embankment and road are very spacious after being completed, and everyone is happy. But we rarely see the street lights on even though they have been installed for a long time.

Only on holidays, the lights were on for a few weeks and then turned off until now," said Mr. Khoa.

According to Giao thong Newspaper reporters, the Cai Son canal renovation project is currently very spacious, with railings, sidewalks, roads behind the embankment, trees and lighting systems completed. However, at night, this road is still plunged into darkness.

Local people are concerned that the lighting system is not effective at night, causing traffic insecurity and not ensuring security and order.

Vì sao đường kè trăm tỷ ở Cần Thơ có đèn nhưng vẫn tối om?- Ảnh 3.

The embankment system and the road behind the embankment on the right bank of Cai Son canal are very spacious. Photo: Nguyen Viet.

Responding to reporters from Giao Thong Newspaper, Mr. Nguyen Van Phuc, Deputy Director of the ODA Project Management Board of Can Tho City, said that the project has been completed, only the work of acceptance and handover to the People's Committee of Ninh Kieu District for management and exploitation remains.

"Ninh Kieu District will take over and manage the project, including tree care and paying for electricity. The contractor will also turn on the street lights for a while, but they cannot pay for electricity forever because the project has not been handed over yet.

We are handing over the project to the district and will quickly light up the streets for people in this area," said Mr. Phuc.

Speaking further on this issue, Mr. Phan Thanh Dien, Head of the Urban Management Department of Ninh Kieu District, said that after the inspection, the unit will submit the results to the District People's Committee to decide on the handover of the project. After that, the department will sign a contract with the electricity company to light up the streets.

Previously, the Urban Management Department had inspected this project and requested the investor and contractor to fix and complete some items, which took time.

"The relevant parties will soon complete the handover work to light up the streets for the people this month," Mr. Dien added.

>>> Some images recorded at the Cai Son - Muong Khai canal renovation project:

Vì sao đường kè trăm tỷ ở Cần Thơ có đèn nhưng vẫn tối om?- Ảnh 4.

The right bank of Cai Son canal seen from Cai Son bridge, many years ago was a low-lying area with several landslides and flooding during heavy rains and high tides. Photo: Nguyen Viet.

Vì sao đường kè trăm tỷ ở Cần Thơ có đèn nhưng vẫn tối om?- Ảnh 5.

The completed embankment creates landscape and contributes to urban beautification for Ninh Kieu and Binh Thuy districts. Photo: Nguyen Viet.

Vì sao đường kè trăm tỷ ở Cần Thơ có đèn nhưng vẫn tối om?- Ảnh 6.

People expect the project to be handed over to local authorities for management and use so that the street lights can be lit every day. Photo: Nguyen Viet.

Vì sao đường kè trăm tỷ ở Cần Thơ có đèn nhưng vẫn tối om?- Ảnh 7.

The operation of the road lighting system behind the embankment is very meaningful to the people here. In addition to ensuring traffic safety and security, it also contributes to improving people's lives. Photo: Nguyen Viet.



Source: https://www.baogiaothong.vn/vi-sao-duong-ke-tram-ty-o-can-tho-co-den-nhung-van-toi-om-192240701150430135.htm

Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product