On May 10, Mr. Phan Truong Thanh, Head of the Planning Department of the Hanoi Department of Transport, informed the press about the project to renovate and expand Lang Road (Ring Road 2 from Nga Tu So to Cau Giay, including both elevated and low-lying sections).
According to Mr. Thanh, the Department of Transport has recently submitted to the Hanoi People's Committee 11 transport infrastructure investment projects for consideration. Among them is the Lang Road expansion project (length 3.8km) with a proposed total investment of more than 21,000 billion VND (the lower section is less than 17,000 billion VND; the elevated section is nearly 3,900 billion VND).
According to the initial plan, the city prioritized building a lower section with a cross-section width of 53.5m (twice the current Lang road with a cross-section width of 10.5m each way), length of 3.8km.
Regarding the above proposal, some opinions of the people and experts said that the investment cost is large, the expanded road is only 3.8km long but the estimated cost is up to more than 21,000 billion VND. If this fund is used for urban railway, it will be more effective. Besides, the site clearance work is complicated, leading to the risk of the project being prolonged.
Regarding this, Mr. Thanh said that according to the planning of Hanoi's Ring Road 2, the total length is 39km, currently 6.1km has not been renovated or expanded. Of which, the Nga Tu So - Cau Giay section (coinciding with the current Lang road) is 3.8km long and the 2.3km section is in the area north of the Red River.
According to Mr. Thanh, prioritizing the completion of closed investment in the Beltway 2 route according to the plan is necessary. However, the related information is preliminary research, the total investment of the project of more than 21,000 billion VND is only an estimated figure.
According to the Head of the Planning Department of the Department of Transport, the department has selected a consulting unit to conduct specific and thorough research, from which to propose specific investment scenarios and plans.
“The responsibility of the state management agency is to choose the most suitable and feasible option. For complex and specific projects like this one, we must be even more cautious,” Mr. Thanh emphasized.
Mr. Thanh said that right from the preliminary research stage, the Department of Transport has considered different options, such as: Expanding Belt 2 towards To Lich River; building Belt 2 on an elevated road towards To Lich River, not depending on the expansion project below and preserving the existing row of mahogany trees; building an urban railway instead of expanding Belt 2 above and below...
From there, the Department of Transport has given a "task" with many requirements to the consulting unit, from calculating technical factors, drainage, environment, investment efficiency,... to minimize the impact on people in the project area as well as have a plan to preserve the perennial rosewood trees.
In addition, to implement this project, the city must also balance capital sources, because Hanoi is focusing resources on Beltway 4 - Capital Region.
“This is a complex project, which will be widely consulted with experts, scientists , and people, especially those in the project's impact area. The project appraisal process is very strict and careful. At the earliest, the overall project will be completed by the end of 2024 to be submitted to the City People's Council for consideration,” said Mr. Thanh.
Doubling the width of Lang Road, the traffic jam 'hot spot' is cooled down
Hanoi doubles the width of Lang road, solving the traffic jam problem at So Intersection
Hanoi proposes 8,500 billion to build an elevated road from Nga Tu So to Cau Giay
Source: https://vietnamnet.vn/3-phuong-an-de-du-an-duong-lang-it-giai-phong-mat-bang-bao-ton-hang-cay-xanh-2279526.html
Comment (0)