Chairman of the Provincial People's Committee Le Ngoc Chau inspected the progress of a number of public investment projects in the province.

On the morning of May 31, comrade Le Ngoc Chau, Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Hai Duong province inspected the implementation of a number of public investment projects in Hai Duong city and Tu Ky district.

Báo Hải DươngBáo Hải Dương31/05/2025

president(1).jpg
Comrade Le Ngoc Chau, Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of Hai Duong province inspected the investment project to build Ta Quang Buu apartment complex, Binh Han ward, Hai Duong city.

Also attending were representatives of leaders of a number of relevant departments, branches and units.

Inspecting the Ta Quang Buu Apartment Construction Investment Project in Binh Han Ward, Hai Duong City, Chairman of Hai Duong Provincial People's Committee Le Ngoc Chau acknowledged the positivity and urgency of the investor and contractors. In the context of many arising difficulties, especially the increasing prices of raw materials such as steel, construction sand, bricks, etc., the Chairman of the Provincial People's Committee requested contractors to carefully calculate and be proactive in input materials, not to be passive, affecting the progress and quality of the project.

Taking advantage of favorable weather, units flexibly organized construction and transported materials, limiting the impact on the lives of surrounding residents, ensuring absolute safety during project construction.

apartment-2.jpg
Ta Quang Buu apartment project with a scale of 390 apartments

The Chairman of the Provincial People's Committee requested the construction units to arrange appropriate human resources, calculate the progress, and complete the reconstruction of the detailed construction plan by June 5 in the spirit of shortening the construction time and completing the project in 2025 (the plan is the end of February 2026).

The Chairman of the Provincial People's Committee noted that "social housing is not cheap housing" so the quality of construction, materials, techniques, and aesthetics must be guaranteed like commercial housing.

chairman-1.jpg
Chairman of Hai Duong Provincial People's Committee Le Ngoc Chau inspected the Project to upgrade and expand Provincial Road 391 from Hai Duong City to the East-West axis road, Hai Duong Province in Hai Duong City.

Inspecting the project to upgrade and expand provincial road 391 from Hai Duong city to the East-West axis of Hai Duong province, in Hai Duong city and Tu Ky district, Chairman of the provincial People's Committee Le Ngoc Chau emphasized that this is a key project of special importance not only to Hai Duong city, Tu Ky district but also to the whole Hai Duong province. The project serves both the development of traffic and inter-regional connectivity and is also a political task of the province.

The Chairman of the Provincial People's Committee requested localities to establish working groups, directly dialogue, and mobilize people to agree on site clearance for project implementation . Mobilize the entire political system to participate, urgently deploy, and assign specific tasks to hand over clean site to the construction contractor in June 2025.

check-your-personal-identity.jpg
The Chairman of the Provincial People's Committee requested localities to establish working groups, directly dialogue, and mobilize people's consensus.

Localities must clearly define boundaries, prevent encroachment after site clearance, and strictly manage clean land funds. The determination of land origin must be accurate, ensuring reasonable and realistic compensation levels. In the spirit of strictly complying with legal regulations, people enjoy the highest level of policies, site clearance work must ensure fairness, transparency, and avoid harassment and negativity.

project-396.jpg
Construction site of the project to renovate and upgrade provincial road 396 extension (section connecting from provincial road 391 to provincial road 390)

Inspecting the project to renovate and upgrade the extended provincial road 396 (the section connecting provincial road 391 to provincial road 390), the Chairman of the Provincial People's Committee requested contractors to calculate and organize construction reasonably, making the most of favorable weather conditions. Mobilize sufficient machinery, human resources, and materials to speed up the project's progress. Flexibly apply measures to remove difficulties arising during the implementation process. Investors and contractors proactively assess the field, closely follow weather developments, have scientific construction plans, speed up progress while still ensuring the requirements of technical standards, aesthetics, and safety of the project.

Ta Quang Buu apartment project with a scale of 390 social housing units in Binh Han ward (Hai Duong city) includes 2 apartment buildings. CT1 apartment building has a scale of 18 floors, the construction area of ​​the first floor is 1,120 m 2 , the total construction floor area is 20,217 m 2. Of which, 240 social housing apartments have an area of ​​45 - 62 m 2. CT2 apartment building has a scale of 18 floors, the construction area of ​​the first floor is 770 m 2 , the total floor area is 13,484 m 2. Of which, there are 150 social housing apartments, the apartment area is from 45 - 62 m 2 . The project started construction in January 2025, with a total investment of more than 329.5 billion VND, invested by the Provincial Construction Investment Project Management Board, and is expected to be completed by the end of February 2026.

The project to upgrade and expand provincial road 391 from Hai Duong city to the East-West axis of Hai Duong province has a total length of 13.87 km, with a total investment of more than 1,392 billion VND. The project consists of 3 sections: sections 1 and 3 are renovated to the scale of a grade III plain road, with a roadbed width of 17.5 m and a design speed of 80 km/h; section 2 is newly built with a roadbed width of 21 m and a design speed of 60 km/h. The bridge section includes the construction of an additional bridge unit at km9+700 and an overpass unit over the Hanoi - Hai Phong expressway, with a bridge width of 12 m.

The project to improve and upgrade the extended Provincial Road 396 (the section connecting Provincial Road 391 to Provincial Road 390) is 7.61 km long (of which 3.66 km is in Thanh Ha district; 3.95 km is in Tu Ky district). The total investment of the project is over VND 846 billion, with the Provincial Construction Investment Project Management Board as the investor. According to the contract, the package will start construction in February 2025 and be completed in October 2026.

SONG HA

Source: https://baohaiduong.vn/chu-tich-ubnd-tinh-le-ngoc-chau-kiem-tra-tien-do-mot-so-du-an-dau-tu-cong-tren-dia-ban-tinh-412851.html


Comment (0)

No data
No data

Same category

Enjoy the top fireworks at the opening night of the 2025 Da Nang International Fireworks Festival
Da Nang International Fireworks Festival 2025 (DIFF 2025) is the longest in history
Hundreds of colorful offering trays sold on the occasion of the Duanwu Festival
Ninh Thuan's infinity beach is most beautiful until the end of June, don't miss it!

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product