According to the Management Board of Investment and Construction Projects of the Agriculture and Rural Development Sector of Tay Ninh Province (MB), up to now, the Tha La reservoir repair project (Tan Chau district) has completed over 90% of the construction volume, including items such as spillway and installation of gate valves, earth dam, concrete dam roof, and earth retaining wall. The canal system alone has been concreted to complete 3,893m, reaching over 100% of the volume.
The unit is implementing the construction of the retaining wall of the landscape area and the old spillway. By May 30, 2025, the earthworks of the landscape area will be completed.
Accordingly, the Tha La lake repair project will complete the dam surface asphalt, complete the landscape architecture and put it into operation by the end of 2025, contributing to the local socio-economic development.
The total investment of the project is 280 billion VND, with the scale of investment, repair, upgrade, and renovation of construction items including: upgrading and repairing the main dam; building a new spillway at the old riverbed; building a traffic bridge across the spillway; completely clearing the bottom discharge culvert; at the same time, the project also repairs the main canal and dredges the Thanh Dong drainage canal.
On November 25, 2022, the Ministry of Agriculture and Rural Development (now the Ministry of Agriculture and Environment) approved the Tha La reservoir repair project. The total investment is 280 billion VND, with the scale of investment, repair, upgrade, and renovation of construction items including: upgrading and repairing the main dam; building a new spillway at the old riverbed; building a traffic bridge across the spillway; completely clearing the bottom discharge culvert; At the same time, the project also repairs the main canal and dredges the Thanh Dong drainage canal.
The project is invested by the Management Board of Investment and Construction Projects of the Agriculture and Rural Development Department of Tay Ninh Province. After the decision was approved, on December 28, 2023, the project officially started construction.
Tha La Reservoir was built in 2005, formed by the construction of a dam on Tha La stream, regulated by a rubber dam, is a relatively large branch of the Saigon River, originating from the Vietnam - Cambodia border area, the main stream length is 34 km, with a capacity of 27.43 million m3 of water. The lake is responsible for providing water for agricultural production for more than 2,700 ha/crop for Tan Chau district.
When completed, Tha La reservoir will provide water for agricultural production, industry, people's daily life and expand the water supply area for the water plant in Tan Chau district with a capacity of 20,000 m3/day and night.
This year, because the water level of Tha La Lake is not as low as in previous years, the construction encountered some difficulties, and the volume of filling is large. Regarding technical requirements, we have to wait for subsidence over time. According to the Project Management Board, the project will be completed by November 2025, ensuring the architectural progress of the landscape area by the end of 2025.
Tam Giang
Source: https://baotayninh.vn/cong-trinh-nang-cap-cai-tao-ho-tha-la-huyen-tan-chau-hoan-thanh-tren-90-khoi-luong-cong-viec-a189189.html