Hau Loc Power workers operate Hau Loc intermediate transformer station.
With the goal of managing and operating the power grid safely and effectively in all situations, serving socio -economic development in the hot season, Hau Loc Power Company has been implementing solutions to effectively implement the instructions of the Northern Power Corporation in general and Thanh Hoa Power Company in particular.
“In recent years, Hau Loc Power has made efforts to meet the demand for electricity for socio-economic development and people's daily life. Along with proactive investment in upgrading and renovating the power system, Hau Loc Power has focused on solutions to thoroughly overcome the shortcomings and limitations of 2024. In particular, focusing on improving the quality of human resources providing electricity services, both professional expertise and communication skills, handling situations, especially the team of officers and employees (CBCNV) who communicate directly with customers. Coordinate the implementation of communication programs to increase the rate of customers participating in cashless electricity payment, using electricity economically and efficiently, providing electricity services through electronic transactions and the National Public Service Portal... Organize planning and implementation to overcome shortcomings including the electricity metering system, preventing commercial losses. At the same time, review and complete the standardization of customer information at on-site. Strictly implement programs, plans and specific measures to continue reducing power loss (TTĐN) on the grid; synthesize, analyze and identify losses after public substations and each medium-voltage line; give top priority to the criteria for reducing TTĐN when performing tasks. In operation management, strengthen technical management of operation and labor safety to meet production and business requirements. Improve the quality of safety work,education and propaganda, regularly remind workers to be aware of protecting themselves and their colleagues; improve the quality of electrical safety training and coaching for workers. Inspection of production sites must be regular from the power supply to production teams. Develop plans to prevent and combat labor accidents" - Mr. Tran Van Chuong, Director of Hau Loc Power Company shared.
With the investment of Thanh Hoa Electricity Company, in the first months of 2025, Hau Loc Electricity has completed 35 regular repair items (SCTX) with a total value of 9 billion VND. Of which, the SCTX items are at the 0.4kV line after Hai Loc 1 substation, the 0.4kV line after Hoa Loc 1 substation; the 0.4kV line after Hoa Loc commune substation No. 4, the 0.4kV line after Hoa Truong, Hoa Phu, Hoa Trung substations (Hoa Loc commune), the 0.4kV line after Lien Loc 1 substation, the rural low-voltage grid in Phu Loc commune with a total length of 15km, helping to reduce power outages and potential risks causing unsafety. Completed 2 major repair items of medium-voltage lines with a total length of 1.126km of renovated lines. Invest in the construction of 5 items with a value of 129.5 billion VND including: overload prevention works for distribution substations in Loc Son, Thanh Loc, Xuan Loc communes, Hau Loc town. Hau Loc Power Company coordinates with contractors to implement projects to upgrade 10kV power lines to 22kV operation level to synchronize with the Hau Loc 2 110kV station project, which has been put into use since the beginning of 2025, ensuring safe and qualified power supply, meeting the increasing demand for electricity. The 2024 TTĐN result decreased to 4.57%.
With the goal of safely operating the power system, providing continuous power to serve the political, socio-economic, production and daily life requirements of local people, especially during the peak hot days, Hau Loc Power Company has assigned 100% of its employees to take shifts to closely monitor weather developments and load growth; review and inspect the power grid situation; establish flexible and reasonable power supply methods, minimize power interruptions due to overload; promptly respond to unusual incidents. Fully prepare materials, equipment, means, and human resources according to the "4 on-site" motto, take shifts 24/24 hours at the power company, the power management team, be ready to be present promptly, mobilize resources to proactively handle sudden incidents as quickly as possible, and restore power to people and agencies and units. In addition, Hau Loc Electricity proactively propagates and encourages customers to apply measures to use electricity economically and share difficulties with the electricity industry during hot weather. Every citizen and business should raise awareness of saving electricity anytime, anywhere. Turning off devices when not in use not only saves money for families, agencies, and businesses, but also contributes to saving electricity for the country.
Hau Loc is one of the areas where saline intrusion and flooding often occur, causing difficulties in providing irrigation water for agricultural production. Therefore, Hau Loc Power Company has coordinated with Hau Loc District Irrigation Branch to proactively check the power system serving pumping stations, prepare spare materials and equipment, energize and test-operate the works, ensuring that 100% of the existing pumps are currently effective in pumping irrigation water, preventing drought in hot seasons, and pumping to drain flooding in rainy and stormy seasons.
Hau Loc Power Company has strengthened inspection, prevented violations from arising, coordinated with communes, towns and related units of the district to strictly handle cases of violations of the high-voltage grid safety corridor. Architectural parts that seriously violate the corridor and are at risk of causing incidents during rain and storms have been handled, the corridor has been cleared, ensuring a safe distance from the grid; the Government's regulations on the safety of high-voltage grid works have been disseminated. The unit has basically thoroughly handled houses and constructions that violate the high-voltage grid safety corridor, avoiding unpredictable dangers. Trimmed and cleared the grid corridor, architectural parts that seriously violate the corridor and are at risk of causing incidents, ensuring a safe distance from the high-voltage grid.
In fact, in 2024 and the first months of 2025, the unit has proactively and effectively implemented plans to respond to and handle incidents, using materials and equipment according to the "4 on-site" motto, promptly organizing to overcome power outages at transformer stations, and soon restoring power to production activities and people's lives in the coastal area of Hau Loc district.
In the long term, Thanh Hoa Electricity Company is requested to mobilize investment capital to upgrade and renovate the power system in Hau Loc district to ensure modernity and synchronization, meeting the requirements of improving the quality of electricity, serving well the requirements of socio-economic development, ensuring political stability, security, national defense and people's lives in the area.
Article and photos: Thu Hoa