Thuan An seaport overpass is nearing completion. Photo: Bao Chau

Timely capital addition

The medium-term urban development plan for the period 2021 - 2025 was approved by the Provincial People's Council (now the city) in Resolution No. 111/NQ-HDND dated October 14, 2021 and assigned by the Provincial People's Committee (now the city) in Decision No. 2755/QD-UBND dated October 29, 2021. Many important projects with spillover effects have contributed to promoting the local economy , including the coastal road project and bridge through Thuan An estuary, Nguyen Hoang road project and Huong river overpass, urban beautification projects, natural disaster prevention and control projects, etc.

According to the Department of Finance's assessment, in nearly 5 years of implementation, the city has identified a number of projects with slow implementation progress, unable to fully utilize the assigned medium-term capital; a number of tasks and projects have been completed, no longer need capital and timely supplemented capital to speed up the implementation progress of key, urgent projects with good disbursement capacity. To ensure the progress of disbursement of public investment capital, last October, the City People's Committee also submitted to the City People's Council an adjustment to the medium-term public investment plan for the period 2021 - 2025 from the local budget.

Renovation projects along the Perfume River contribute to creating a new urban landscape.

Accordingly, the City People's Committee adjusted down 19 billion VND in the medium-term public investment plan for the period of 2021 - 2025 for the coastal road section and bridge through Thuan An estuary project to prioritize payment of central budget capital, in accordance with the implementation capacity in 2025. Adjusted up 19 billion VND in the medium-term public investment plan for the period of 2021 - 2025 to implement the projects: Investment in supporting the modernization of the Mobile Police force of Hue City Police to ensure security and social order and safety of the city and the Project of Clearance of land and infrastructure outside the fence of the Project of Expansion of Hue Central Hospital, Facility 2 to ensure the commencement of the project in 2025.

Also according to the Department of Finance, this year, Hue city has adjusted the medium-term public investment plan 4 times with a total capital of 70 billion VND. The flexible and timely adjustment of the medium-term public investment plan for the period 2021 - 2025 has contributed to promoting the city's public investment disbursement rate. Currently, Hue city is in the group of localities with disbursement higher than the national average. On September 17, 2025, Hue was commended by the Prime Minister at the conference to promote public investment (3rd time).

Strengthening post-control solutions

Along with the work of adjusting the capital plan flexibly and promptly from slow-disbursement projects to projects with high capital demand and disbursement capacity according to regulations, Hue city also resolutely implemented many solutions to promote the disbursement of public investment capital. In particular, the city requires the initiative of departments, branches, localities and investors to strive to disburse 100% of the capital plan for 2025 assigned by the Prime Minister. Promote the effectiveness of the working groups led by the Chairman and Vice Chairmen of the City People's Committee, with directors of departments as members to guide, strengthen urging, inspect, supervise, handle difficulties, speed up the implementation progress of projects; link the acceleration of public investment capital disbursement progress with ensuring the quality of works, preventing negativity, loss, waste and violations of legal regulations.

At the same time, focus on solving the work of site clearance, compensation, resettlement support; review and ensure adequate supply of raw materials for projects, especially key projects. Require investors to make detailed disbursement plans for each project by quarter and month and strictly comply with the committed plan; strengthen inspection and supervision of the site, urge contractors and consultants to speed up progress...

Currently, key, inter-regional, and influential urban development projects of Hue city are progressing well and disbursing funds. It is expected that in 2025, some important infrastructure projects of the city will be completed early, such as the coastal road project and the bridge through Thuan An estuary, which is expected to be technically open to traffic in the fourth quarter of 2025... Urban beautification projects such as the Hue City Water Environment Improvement Project and the Type II Urban Development Program Project (green cities) have also completed the project extension procedures and have been supplemented with capital to speed up the completion progress in 2025. Investment projects for infrastructure development in economic zones and industrial parks such as the Chan May Port Breakwater Project Phase 2 and main roads in industrial parks will be fully invested in 2025. The city is focusing on speeding up the progress of investment projects in resettlement areas and cemeteries to serve the site clearance work of the North-South High-speed Railway Project through Hue City and urgently completing investment procedures to build boarding schools for primary and secondary schools in Hue. border communes of A Luoi 1, 2, 3, 4, 5.

According to data from the Department of Finance, as of September 25, 2025, the city has disbursed VND 3,581 billion/VND 4,821 billion, reaching 74.3% of the capital plan assigned by the Prime Minister, belonging to the group of localities with a disbursement rate higher than the national average of 46.3%. Of which, local budget capital has disbursed VND 2,736 billion/VND 3,348 billion, reaching 81.7% of the plan; domestic central budget capital has disbursed VND 809 billion/VND 1,301 billion, reaching 62.2% of the plan; foreign central budget capital (ODA) has disbursed VND 35.3 billion/VND 172 billion, reaching 20.5% of the plan. If calculating additional capital sources allocated during the year, in the past 9 months, the city disbursed 3,581 billion VND/7,488 billion VND, reaching 47.8% of the plan.


Article and photos: Hoang Anh