Urging the progress of 2 traffic projects in poor district of Dak Nong

On April 4, Mr. Tran Dinh Ninh, Acting Director of the Department of Finance of Dak Nong province led a working delegation of the province to inspect and urge the acceleration of public investment disbursement in Dak Nong district...

Báo Đắk NôngBáo Đắk Nông04/04/2025

The working group inspected the Project of the roads of the Cultural - Commercial Center of Dak Glong district; the project of the inter-commune road of Dak Plao - Dak R'mang - Dak Som. These projects are invested by the People's Committee of Dak Glong district.

dsc01570(1).jpg
The provincial working delegation inspected and urged to accelerate the disbursement of public investment in 2025 in Dak Glong district (Dak Nong)

According to the report of Dak Glong District People's Committee, the two projects have a total investment of 205 billion VND. To date, the district has disbursed 121.7 billion VND, reaching 59.4% of the allocated capital.

Specifically, the Dak Glong District Cultural and Commercial Center Road Project has a length of 3.34km, with a total investment of VND95 billion. Up to now, the project has achieved 60% progress, disbursed VND68.5 billion, accounting for 72% of the allocated capital.

This project is still stuck with 2 households due to the lack of agreement on compensation prices. In addition, the project is also facing difficulties in sourcing land for embankment…

dsc01594(1).jpg
The Dak Plao - Dak R'mang - Dak Som inter-commune road project has a total investment of 110 billion VND, progress reaching 25%.

The Dak Plao - Dak R'mang - Dak Som inter-commune road project has a length of nearly 16km, with a total investment of 110 billion VND. To date, the project's construction volume has reached 25%.

The district has disbursed more than 53 billion VND, reaching 48.4% of the allocated capital. The project still has 2 households that have not agreed to hand over the land, 12 households are being considered for approval of the compensation plan by the District People's Committee, and some households have not agreed to donate land.

dsc01587(1).jpg
Construction unit of Dak Plao - Dak R'mang - Dak Som inter-commune road project reports progress to the working delegation

In addition to the above difficulties, Dak Glong district proposed that the provincial authorities add a plan to auction and grant the right to exploit the landfill material mine in Quang Khe commune to serve the projects.

dsc01675(1).jpg
Mr. Tran Dinh Ninh, Acting Director of Dak Nong Provincial Department of Finance, spoke at the meeting.

Mr. Tran Dinh Ninh, Acting Director of the Department of Finance of Dak Nong province, assessed that the district's projects are basically being implemented on schedule.

However, contractors and investors need to create a progress table to monitor, supervise, urge, and jointly resolve difficulties during project implementation. Construction units work overtime and add more manpower to carry out the project according to the committed schedule...

Source: https://baodaknong.vn/doc-thuc-tien-do-2-du-an-giao-thong-o-huyen-ngheo-dak-nong-248281.html


Comment (0)

No data
No data

Same tag

Same category

Hanoi pho restaurants
Admire the green mountains and blue waters of Cao Bang
Close-up of the 'appearing and disappearing' cross-sea walking path in Binh Dinh
Ho Chi Minh City is growing into a modern "super city".

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product