Vice Chairman of the Provincial People's Committee Truong Cong Thai chaired the meeting. The meeting was connected online to localities in the province.
According to the report of the Department of Finance, the total public investment plan assigned by the province in 2025 is more than 9,401 billion VND, of which more than 7,565 billion VND is assigned to provincial-level projects. By the end of April 30, 2025, the detailed allocation to each project category was nearly 6,783 billion VND (equal to 91.6% of the plan).
As of April 30, 2025, units have disbursed more than VND 1,384 billion (equal to 20.4% of the plan, up 8% compared to the previous month, with an increase of more than VND 514 billion). Of which, the central budget has disbursed more than VND 1,015 billion (19.6% of the plan); local budget has disbursed nearly VND 369 billion (23% of the plan).
Vice Chairman of the Provincial People's Committee Truong Cong Thai spoke at the meeting. |
If calculated according to the central capital assigned according to the data reported by the Ministry of Finance , the province has disbursed 22.97% of the plan, 7.41% higher than the national average (the national average is 15.56%), ranking second in disbursement for the 5 Central Highlands provinces, ranking 18th out of 63 provinces and cities and ranking 23rd out of 111 units assigned to implement the public investment plan.
Although the disbursement rate in the first 4 months of the year was quite good, it still did not meet the set plan, due to a number of reasons, including a number of newly started projects in the 2024 plan, in 2025 they are in the process of completing the payment volume of the 2024 plan; a number of completed projects that have been handed over and put into use are arranged in the 2025 plan, currently the investors are completing the procedures for approving project settlement and warranty work, so no disbursement has been made. In the 2025 plan, there are a number of newly started projects that are in the process of bidding for construction and installation, so there is no volume to disburse.
Director of the Department of Finance Vo Ngoc Tuyen reported on the implementation and disbursement of public investment plans. |
In addition, the coordination between the investor and local authorities to carry out compensation and site clearance has not been really active; compensation, support and resettlement work has been slow; planning of land mines for exploitation and implementation of projects and adjusting land use planning and plans have been slow.
At the meeting, delegates spent a lot of time reporting and sharing difficulties and obstacles in the process of implementing projects. From there, solutions were proposed to speed up the implementation progress and disbursement of capital for basic construction in the coming time.
Representatives of the Provincial Project Management Board for Transport Works and Rural Development Agriculture reported at the meeting. |
Concluding the meeting, Vice Chairman of the Provincial People's Committee Truong Cong Thai requested departments, branches, sectors and investors to urgently speed up the implementation progress and disburse funds as soon as possible, avoiding the situation of capital construction remaining at the end of the year. In particular, it is necessary to actively carry out compensation and site clearance work to promptly hand over the site to the construction unit according to the project implementation schedule.
At the same time, review and guide the dossier on mineral exploitation as common construction materials for investment projects. The Provincial People's Committee grants licenses for mineral exploration and exploitation according to regulations.
For units assigned with land use fee collection plans, they must promptly implement plans to collect land use fees and land sale fees to ensure investment capital for projects included in the plan.
Source: https://baodaklak.vn/kinh-te/202505/khan-truong-day-nhanh-tien-do-giai-ngan-von-dau-tu-cong-c2a05d4/