The project to expand Duong Quang Ham Street (Go Vap District, Ho Chi Minh City) aims to be completed and open to traffic by the end of 2024. However, Ho Chi Minh City Electricity affirmed that the unit cannot complete the relocation of the power pole in 2024.
Duong Quang Ham Street (Go Vap District, Ho Chi Minh City) is being upgraded and expanded to 6 lanes with a total investment of about 2,300 billion VND.
The Duong Quang Ham Street expansion project is being accelerated. Photo: MQ
This route is expected to be one of the backbone roads of Go Vap district, sharing traffic pressure with neighboring routes such as Phan Van Tri, Nguyen Thai Son, Le Duc Tho...
According to the Management Board of Traffic Construction Investment Projects (Traffic Board, investor), the Duong Quang Ham Street expansion project has a total length of about 2.5km, connecting from Binh Thanh District to Go Vap Cultural Park.
To date, the first section of the project adjacent to the railway (section through Binh Thanh District) is almost completed. Contractors are focusing on constructing the drainage system and expanding the road surface within the area of land handover.
However, the contractor still encountered some difficulties and problems due to the existing medium and low voltage grids that have not been recovered, affecting the project completion progress.
The Traffic Department requested the electricity company to urgently pull underground cables within the area where the sewers and technical tanks have been handed over before November 25 to have time to lay asphalt concrete on the road surface and pave the sidewalks within the area that does not obstruct the site.
Ho Chi Minh City Electricity said it cannot relocate or underground the power system in 2024. Photo: My Quynh
On October 30, speaking with Giao Thong Newspaper reporters, Mr. Tran Dien Anh, Deputy Director of the Ho Chi Minh City Power Distribution Grid Project Management Board (Ho Chi Minh City Power Corporation) said that for the Duong Quang Ham road project, the unit cannot complete the relocation and undergrounding of the power system in 2024.
According to Mr. Anh, in principle, when the site is handed over to the electricity company, then the unit can start pulling cables and construction. This process takes about 6 months, so it will not be completed until the second quarter of 2025.
Mr. Anh emphasized that electricity construction is not like road construction. The power pulling and connection must be done through the route; it cannot be done in a way that allows for the section to be done. The underground grid, switching to underground wires, and the power cannot be cut off continuously because electricity must be supplied to the people.
The system of electric poles blocking Duong Quang Ham street. Clip: My Quynh
"Currently, the first difficulty is that the site is not yet completed and has not been handed over; second, the work of purchasing electrical equipment from abroad needs to follow the process and bidding, and it will take until the end of the year to have enough electrical materials. For example, Tan Ky Tan Quy road, we received the site in June 2024, and it will not be completed until November 15. Only after the road is completed can the electrical part be done, it is impossible for the electrical part to be completed immediately after the road is completed," said Mr. Anh.
It is known that the electricity department is currently coordinating with the contractor to bury the pipes and cables as the road construction progresses; ensuring that after the asphalt road is completed, it will not be dug up to bury the electricity.
After the road section is completed, the city's electricity company will install equipment to convert the grid from medium voltage to low voltage.
Recently, Vice Chairman of Ho Chi Minh City People's Committee Nguyen Van Dung inspected the Duong Quang Ham Street expansion project. The leaders of the City People's Committee requested Ho Chi Minh City Electricity Corporation to study the relocation plan as soon as possible to hand over the site to the Traffic Department so that the road can be opened to traffic by the end of 2024 as planned.
Up to now, Go Vap District People's Committee has handed over the site to the Traffic Department in 388/425 cases, 37 cases have not been handed over, with a total length of about 590m that has not been constructed.
The Go Vap District People's Committee has reviewed and issued a decision to arrange resettlement land for households. At the same time, it coordinated with the Housing Management and Construction Inspection Center to sign resettlement contracts for 25 cases; hand over land to 24 cases...
All households that have not received money or handed over the premises have been contacted and all have agreed to receive money and committed to handing over the premises.
Source: https://www.baogiaothong.vn/tphcm-khong-the-di-doi-he-thong-dien-tren-duong-duong-quang-ham-trong-nam-2024-192241030140418185.htm