The province has disbursed 1,499 billion/3,893 billion VND of local budget balance capital, reaching a rate of 39%. However, the disbursement rate of central budget capital has only reached 8%. The province is directing, for projects that have been finalized and completed and put into use: Urgently approve finalization, disburse all allocated capital; strengthen urging contractors to speed up construction progress; focus on completing legal procedures, accepting completed volume to be eligible for payment to contractors in accordance with regulations for transitional projects. Particularly, newly started projects need to complete documents, develop capital allocation plans to submit to the regular People's Council meeting. This year, the province has 15/17 projects with central funding that must be completed and put into use/.