The investment project to build the 1,200-bed Ca Mau General Hospital has the largest capital source in Ca Mau province, but because it has just started construction, the disbursement rate is low - Photo: THANH HUYEN
On May 14, Mr. Tran Cong Khanh - Deputy Director of the Department of Finance of Ca Mau province - said that the total public investment plan for 2025 (including 2024) of the province is 6,396 billion VND.
Ca Mau Provincial People's Committee has allocated 5,854 billion VND in detail, leaving 542 billion VND unallocated.
By the end of April 2025, Ca Mau province had disbursed VND 1,329 billion, equal to 20% of the capital plan, lower than the disbursement in the same period in 2024 (in the same period, disbursement was 22% of the capital plan).
Some investors were allocated a lot of capital but the disbursement rate was low: Construction Project Management Board (allocated 2,534 billion VND, disbursed 12% of capital); Traffic Project Management Board (allocated 984 billion VND, disbursed 15% of capital); ODA and NGO Project Management Board (allocated 324 billion VND, disbursed 5% of capital)...
According to the Department of Finance, the progress of some large and important projects of Ca Mau province is still slow, some projects have just been given advance contracts at the end of 2024, so there is no volume to disburse in early 2025 such as: Investment project to build Ca Mau General Hospital with a scale of 1,200 beds (VND 2,229 billion, accounting for 35% of the total capital plan of the province); Investment project to build the office building of Ca Mau Provincial Party Committee; Investment project to build resettlement area of hamlet 6B; Project to upgrade and expand the road to the center of Hang Vinh commune...
To disburse funds as planned, the Chairman of the People's Committee of Ca Mau province requested investors and heads of agencies and units to implement solutions to promote disbursement of public investment capital; resolutely and proactively handle and focus on removing difficulties and obstacles related to project implementation.
Focus on priority in direction and operation, associated with the responsibility of heads of units and responsible to the Chairman of the Provincial People's Committee for disbursement results as well as investment efficiency of projects.