The measurement and counting of land and assets attached to land is the basis for the government and competent agencies to develop plans to implement land compensation and recovery; at the same time, support resettlement for people whose land must be recovered to serve the expressway according to regulations.
.jpg)
Participating in the measurement and counting work were representatives of the Investment Project Management Board No. 1, the government and functional agencies of Ward 1 - Bao Loc, representatives of residential groups and households with land and assets attached to the land subject to recovery for the expressway project. The work was carried out smoothly, receiving consensus and high support from the people. The measurement and counting of land, structures, crops and assets attached to the land were carried out in accordance with procedures and in compliance with the provisions of law.
.jpg)
According to the representative of the People's Committee of Ward 1, Bao Loc, in parallel with the measurement and counting work, the local government will coordinate with the departments and branches of the province to develop a plan to implement site clearance according to the overall diagram; at the same time, create a schedule of work items for the Management Board of Investment Project No. 1 to synthesize and complete the general plan of the project to submit to the Provincial People's Committee for consideration and direction.
.jpg)
Ms. Nguyen Thi Kim, a resident whose land was recovered for the expressway project, shared: “The State’s plan to open an expressway is a popular policy, and we strongly support it. After a long wait, the people are very excited about the land, crops, and assets attached to the land being measured and counted. We hope the State will soon implement the project and ensure that compensation, resettlement, vocational training, and employment policies are implemented transparently, objectively, and satisfactorily.”
Similarly, Mr. Nguyen Cong Thanh, a resident whose land is within the scope of the reclamation, said: “My family has an area of agricultural land growing durian, which provides a stable income. After being informed, we completely agreed and are ready to complete the procedures for receiving compensation and handing over the land to the State to implement the project. People only hope to be compensated appropriately and in accordance with regulations.”
.jpg)
Under the direction of the Lam Dong Provincial People's Committee, during the process of localities and functional agencies implementing measurement and counting, the Provincial Land Fund Development Center was assigned to urgently direct and urge the Regional Land Registration Office Branches to closely coordinate with localities and related units. Thereby, promptly handle issues of extracting, measuring, exploiting cadastral information and supporting cadastral map operations to serve the project site clearance work. Periodically, before the 20th of each month, the Center reports the implementation results to the Management Board of Construction Investment Project No. 1 for synthesis and reporting to the Provincial People's Committee.
.jpg)

Localities are required to proactively coordinate with the Construction Investment Project Management Board No. 1, the Provincial Land Fund Development Center and related units to review and unify the plan for site clearance according to the Gantt chart. At the same time, develop a progress table for specific tasks, clearly stating the completion time and tasks of each unit. On that basis, each locality will make a monthly and weekly implementation plan and periodically evaluate the results of each item; the report must fully demonstrate data, specific evidence, and clear proof of the work that has been implemented.
.jpg)
Localities need to proactively coordinate with the Land Fund Development Center to hand over documents and tasks related to compensation, site clearance, and resettlement that the locality has implemented, specifically boundary documents, inventory, list of land recovery notices, etc. and work to be continued; at the same time, review the remaining tasks performed by the locality to coordinate with relevant departments, branches, sectors and units to implement.

Localities need to urgently speed up the selection of consulting units, prepare specific land valuation records for appraisal and approval; at the same time, organize the inventory and statistics of assets on land, ensuring progress according to the Gantt chart. In addition, it is necessary to pay special attention to propaganda and mobilization work, create consensus among the people, ensure publicity and transparency, and limit the occurrence of prolonged complaints and lawsuits.

The Bao Loc - Lien Khuong expressway construction investment project passing through Ward 1 Bao Loc has 32 hectares of agricultural land for perennial crops and 4.6 hectares of other land of 171 households and 1 organization affected by the project.

According to statistics, Ward 1 Bao Loc currently has 61 households with residential land that are eligible for resettlement after land acquisition for the Bao Loc - Lien Khuong Expressway Project. Up to now, the locality has completed the land valuation work to notify affected households, and continues to coordinate with relevant units to complete the land valuation file to serve the project's site clearance work.