Prime Minister requests to start construction of Lao Cai - Hanoi - Hai Phong railway on December 19

With the working spirit of "working during the day is not enough, working at night", the Prime Minister requested to complete procedures and start construction of the Lao Cai - Hanoi - Hai Phong railway on December 19.

VTC NewsVTC News01/05/2025

The above direction was mentioned by Prime Minister Pham Minh Chinh in Official Dispatch No. 54 on accelerating the implementation progress of the Lao Cai - Hanoi - Hai Phong railway project.

To ensure the goal of starting and completing the Project on schedule in 2025; in the spirit of the historic April days "faster, faster; bolder, bolder", the Prime Minister requested the Minister of Construction and Chairmen of the People's Committees of the provinces and cities where the project passes through to urgently and seriously implement the tasks.

The Prime Minister directed to speed up the progress of the Lao Cai - Hanoi - Hai Phong railway project.

The Prime Minister directed to speed up the progress of the Lao Cai - Hanoi - Hai Phong railway project.

Specifically, the Minister of Construction worked with localities to hand over the coordinates of the centerline and the land clearance boundary as a basis for localities to carry out compensation, support, resettlement, survey and design to prepare the project's Feasibility Study Report, to be completed in June.

The Prime Minister assigned the Minister of Construction to direct the Project Management Boards and consulting units to increase human resources and organize the parallel implementation of the work of preparing, appraising and approving the Feasibility Study Report, construction design after basic design, bidding documents, request documents and other procedures of the project (absolutely not letting the latter wait for the former).

" With the working spirit of "working during the day is not enough, working at night", working "through holidays, through Tet, through days off", completing procedures, starting the project on December 19, 2025. If necessary, mobilize human resources from the Hanoi Urban Railway Project Management Board to strengthen and support in the implementation process ", the Prime Minister emphasized.

The Head of Government requested to urgently complete the dossier to submit the National Assembly Resolution on specific mechanisms and policies, especially investment in developing the railway system at the 9th Session of the 15th National Assembly; report to the Government before May 5.

The Prime Minister assigned the Chairmen of the People's Committees of the provinces and cities of Hanoi, Lao Cai, Yen Bai, Phu Tho, Vinh Phuc, Bac Ninh, Hung Yen, Hai Duong, and Hai Phong to establish Steering Committees for site clearance of the project in the localities, headed by the Secretary of the Provincial and Municipal Party Committees.

This needs to be completed before May 5 to focus on directing and mobilizing the entire political system at all levels to organize and implement site clearance work for the project.

At the request of the Prime Minister, all levels, sectors and local agencies closely coordinate with the agencies of the Ministry of Construction and the Railway Project Management Board to receive documents (coordinates of the center line, land clearance boundary); immediately organize the implementation of compensation, support and resettlement of the project. Complete in August to hand over the site to serve the project construction.

During the site clearance process, the Head of Government noted the need to invest in the construction of resettlement areas, ensuring that people have new housing that is at least equal to or better than their old housing; doing a good job of propaganda, mobilization, support, and creating more jobs and livelihoods for local people. If necessary, temporary housing solutions should be provided to stabilize people's lives and ensure project progress.

The Prime Minister requested the Minister of Agriculture and Environment to closely coordinate with the Ministry of Construction and localities to speed up procedures related to the conversion of forest, forest land and rice land use purposes; proactively guide localities to organize the implementation of compensation, support and resettlement of the project, promptly remove obstacles according to assigned functions and tasks.

The Minister of Finance directed to urgently review the central and local regular spending savings in 2025 to prioritize project implementation; report to the Prime Minister in May.

In the telegram, the Prime Minister assigned Deputy Prime Minister Tran Hong Ha to directly monitor, direct and remove difficulties and obstacles of the project.

English

Source: https://vtcnews.vn/thu-tuong-yeu-cau-khoi-cong-duong-sat-lao-cai-ha-noi-hai-phong-ngay-19-12-ar940914.html


Comment (0)

No data
No data

Same category

Da Nang International Fireworks Festival 2025 (DIFF 2025) is the longest in history
Hundreds of colorful offering trays sold on the occasion of the Duanwu Festival
Ninh Thuan's infinity beach is most beautiful until the end of June, don't miss it!
The yellow color of Tam Coc

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product